Request for Price Increase Based on Error in Bid Alleged After Award

B-184238 Jul 30, 1975
Jump To:
Skip to Highlights

Highlights

A contractor requested an increase in price under its contract and an increase in its costs for parts and freight. The contractor was not entitled to a price increase since the contracting officer was not on actual or constructive notice of the mistake prior to the award. A variation of 13 percent between the low and next low bid was not sufficient byitself to constitute constructive notice where a broad range of bids was received. The contractor was not entitled to a price increase due to its increased cost of performance since there was no price escalation clause in the contract.

Downloads

GAO Contacts

Kenneth E. Patton
Managing Associate General Counsel
Office of the General Counsel

Edward (Ed) Goldstein
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries