Please note that a lapse in appropriations has caused GAO to shut down its operations. Therefore, GAO will not be able to publish reports or otherwise update this website until GAO resumes operations. In addition, the vast majority of GAO personnel are not permitted to work. Consequently, calls or emails to agency personnel may not be returned until GAO resumes operations. For details on how the bid protest process will be handled during the shutdown, please see the legal decisions page. For information related to the GAO Personnel Appeals Board (PAB), please see the PAB webpage.

Ambiguous Solicitation Resulted in Nonresponsive Bids

B-183486 Jun 19, 1975
Jump To:
Skip to Highlights

Highlights

The low bidder protested the rejection of its bid as nonresponsive and, after the agency reaffirmed the determination of nonresponsiveness, the third low bidder protested rejection of its bid. The solicitation was subject to conflicting reasonable interpretations and so inadequately expressed the agency's needs that it ensnared bidders into submitting nonresponsive bids. As a result, the solicitation should be canceled and the systems should be resolicited.

Downloads

GAO Contacts

Kenneth E. Patton
Managing Associate General Counsel
Office of the General Counsel

Edward (Ed) Goldstein
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries