Request for Increase in Price of Contract
B-183064
Jun 23, 1975
Skip to Highlights
Highlights
A company requested an increase in the price of its contract after alleging an error in its bid prior to award. An increase may be allowed for materials omitted from worksheet calculations, but the amount claimed for the omission of certain costs cannot be allowed. A claim for additional costs caused by the contractor's decision to change suppliers must be denied since this item was not involved in the erroneous calculation.