B-147612:
Mar 22, 1962
S-23FBO-153 WAS EXECUTED. THE OFFICE BUILDING IN QUESTION WAS SCHEDULED FOR COMPLETION BY APRIL 14. DELIVERY DATE THE CONTRACTOR UNDERTAKES THE RESPONSIBILITY TO HAVE THE PRIVATE AUTOMATIC BRANCH EXCHANGE. "F. LIQUIDATED DAMAGES IN CASE THE CONTRACTOR FAILS TO COMPLETE THE WORK UNDER THIS CONTRACT WITHIN THE SPECIFIED TIME LIMIT AND THE DELAY IS HIS RESPONSIBILITY. THEN THE CONTRACTOR WILL PAY 0.5...