B-147612, MAR. 22, 1962

B-147612: Mar 22, 1962

S-23FBO-153 WAS EXECUTED. THE OFFICE BUILDING IN QUESTION WAS SCHEDULED FOR COMPLETION BY APRIL 14. DELIVERY DATE THE CONTRACTOR UNDERTAKES THE RESPONSIBILITY TO HAVE THE PRIVATE AUTOMATIC BRANCH EXCHANGE. "F. LIQUIDATED DAMAGES IN CASE THE CONTRACTOR FAILS TO COMPLETE THE WORK UNDER THIS CONTRACT WITHIN THE SPECIFIED TIME LIMIT AND THE DELAY IS HIS RESPONSIBILITY. THEN THE CONTRACTOR WILL PAY 0.5...

  • html report icon View Decision (HTML)
B-147612, MAY 8, 1962

B-147612: May 08, 1962

IT WAS REPORTED THAT PRIMARILY THROUGH THE FAILURE OF A SUBCONTRACTOR TO SUPPLY MATERIALS TO THE CONTRACTOR UNDER THE NEW EMBASSY OFFICE BUILDING CONSTRUCTION CONTRACT. THE CONSTRUCTION CONTRACTOR ON THE NEW OFFICE BUILDING WAS UNABLE TO COMPLETE ITS CONTRACT WITH THE DEPARTMENT BY THE SCHEDULED TIME OF APRIL 14. AUTELCO WAS UNABLE TO MEET ITS MARCH 28. IT WAS REQUIRED TO EMPLOY THE SERVICES OF A...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap