ATTORNEYS AT LAW: WE HAVE YOUR LETTER OF JULY 29. THERE IS NOW PENDING IN THE COURT OF CLAIMS PETITION NO. 291-57. THE SAME STATUTORY PROVISIONS AND THE IDENTICAL ISSUES PRESENTED IN THE ALTERNATIVE CLAIMS YOU HAVE PRESENTED TO THIS OFFICE IN THE LETTER OF JULY 29. FINAL ACTION WILL NOT BE TAKEN BY THIS OFFICE ON THE ALTERNATIVE CLAIMS PRESENTED HERE FOR THE PERIOD JULY 1.

B-103761, AUG. 26, 1957

TO ANSELL AND ANSELL, ATTORNEYS AT LAW:

WE HAVE YOUR LETTER OF JULY 29, 1957, PRESENTING ALTERNATIVE CLAIMS ON BEHALF OF CLAUDE WALLACE SHELTON, MAJOR, UNITED STATES ARMY, RETIRED, FOR ADDITIONAL RETIRED PAY FOR THE PERIOD FROM JULY 1, 1947, TO MAY 31, 1951, INCLUSIVE.

THERE IS NOW PENDING IN THE COURT OF CLAIMS PETITION NO. 291-57, FILED JUNE 27, 1957, IN THE CASE OF CLAUDE WALLACE SHELTON V. UNITED STATES, FOR ADDITIONAL RETIRED PAY FOR THE PERIOD FROM JUNE 1, 1951, TO DATE OF JUDGMENT.

THE SAME STATUTORY PROVISIONS AND THE IDENTICAL ISSUES PRESENTED IN THE ALTERNATIVE CLAIMS YOU HAVE PRESENTED TO THIS OFFICE IN THE LETTER OF JULY 29, 1957, APPEAR FOR CONSIDERATION BY THE COURT OF CLAIMS ON THE PETITION NO. 291-57. ACCORDINGLY, FINAL ACTION WILL NOT BE TAKEN BY THIS OFFICE ON THE ALTERNATIVE CLAIMS PRESENTED HERE FOR THE PERIOD JULY 1, 1947, TO MAY 31, 1951, INCLUSIVE, UNTIL THE CONCLUSION OF THE JUDICIAL PROCEEDINGS NOW PENDING IN THE COURT OF CLAIMS.

Apr 23, 2018

Apr 20, 2018

Apr 18, 2018

Apr 17, 2018

  • AeroSage, LLC
    We dismiss in part and deny in part the protests.
    B-415893,B-415894

Apr 16, 2018

Looking for more? Browse all our products here