B-101323:
Sep 30, 1966
GENERAL SERVICES ADMINISTRATION: REFERENCE IS MADE TO LETTER OF SEPTEMBER 9. THE EXAMPLE CITED OF A BASIS FOR SUSPICION OF ERROR IS THAT THE BID IS SIGNIFICANTLY OUT OF LINE WITH THE NEXT HIGH BID OR WITH THE GOVERNMENT'S ESTIMATE. THE CONTRACTING OFFICER SHALL CONSIDER THE BID AS SUBMITTED UNLESS THE AMOUNT OF THE BID IS SO FAR OUT OF LINE WITH THE AMOUNTS OF OTHER BIDS RECEIVED OR WITH THE AMOUN...