Aquaterra Contracting, Inc.
Highlights
Aquaterra Contracting, Inc. protests the rejection of its bid as late under invitation for bids (IFB) No. W912P8-08-B-0019, issued by the Department of the Army, Corps of Engineers, for dolphin replacement work at Calcasieu Lock, Calcasieu Parish, Louisiana.
B-400065, Aquaterra Contracting, Inc., July 14, 2008
Decision
Matter of: Aquaterra Contracting, Inc.
Timothy A. Sullivan, Esq., Payne Hackenbracht & Sullivan, for the protester.
Parag J. Rawal, Esq., and Deena G. Braunstein, Esq., Department of the Army, Corps of Engineers, for the agency.
Susan K. McAuliffe, Esq., and Christine S. Melody, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Protest of agency's rejection of bid as late is denied where bidder's failure to address and label its bid package as instructed by the solicitation was paramount cause of its late arrival to bid opening location.
DECISION
Aquaterra Contracting, Inc. protests the rejection of its bid as late under invitation for bids (IFB) No. W912P8-08-B-0019, issued by the Department of the Army, Corps of Engineers, for dolphin replacement work at Calcasieu Lock, Calcasieu Parish, Louisiana.
The IFB, as amended, required that sealed bids be submitted by on
Aquaterra submitted its bid via commercial carrier in a sealed envelope that failed to identify in any way that the package was time-sensitive or contained a bid (no solicitation number or bid opening information was marked on the envelope); the protester failed to address the envelope to the amended point of contact and failed to address the package to the post office box address identified in the IFB for the submission of bids. Rather, Aquaterra submitted its bid in an envelope addressed to Contracting Officer at the street address of the agency's contracting division, which address was identified in the solicitation amendments as the office that issued the amendments.[2]
Aquaterra's bid package arrived in the agency's mailroom at on February 11. At approximately , the envelope left the mailroom for delivery to the contracting division. At , the contracting specialist identified as the point of contact left her office to conduct the bid opening in a nearby conference room. Five hand-delivered bids were opened at that time; Aquaterra's bid had not reached the contract specialist in time for the bid opening.
The protester's bid package and another firm's bid package were delivered to the contracting division at approximately (the agency reports that while it is possible the bids may have arrived at the contracting division just prior to the bid opening, there is no evidence that shows the actual time of receipt). The agency reports that since the protester's package was only generally addressed to Contracting Officer (where there are 13 contracting officers in that division), and the other bid was addressed to a former agency employee, the packages were left for one of the contracting officers to help identify the correct destinations for the packages. That contracting officer found the packages upon returning from meetings 2 hours later. When she opened Aquaterra's package, she found it contained a bid and forwarded it to the point of contact for the procurement.
The next day, the contracting officer handling the procurement reasoned that, since Aquaterra's bid package and the other firm's bid package had been received at the mailroom approximately 4 hours prior to bid opening, it was government mishandling that caused the bids to arrive at the bid opening location late. After applying the applicable 10-percent price preference for Historically Underutilized Business Zone firms, Aquaterra's bid became low and award was made to the firm. However, in reviewing an agency-level protest filed by the bidder next in line for award, alleging that the Aquaterra bid was submitted late, the contracting officer for the first time recognized that Aquaterra's bid package envelope had not been addressed or labeled as directed by the solicitation. The contracting officer concluded that the firm had significantly contributed to the lateness of its bid, and, finding that government mishandling was not the paramount cause of the lateness of the bid, the contracting officer terminated the award, rejecting the protester's bid as late.[3] This protest followed.
Aquaterra contends that its bid was not late, since it was received by the agency's mailroom, and possibly, by the contracting division, before the bid opening time, and had been in the government's custody between its receipt and the bid opening. In this regard, the protester argues that, even though it did not address its bid package envelope as instructed by the IFB, since the IFB did not specify a particular location for the bid opening, its bid's documented receipt at the agency's mailroom, or the possibility that the bid was in fact delivered to the contracting division before 2 p.m., should be used to measure the timeliness of its bid. Alternatively, the firm argues that if its bid was late, government mishandling in not delivering its bid to the contracting division sooner was the paramount cause of its lateness. While the protester concedes that its own bid package did not provide any indication to the mailroom personnel that the package contained a bid to be sent to the contracting division immediately, it argues that its bid should be considered due to government mishandling, since the other bid package delivered with Aquaterra's to the mailroom was labeled as containing a bid and it too was delivered late to the bid opening from the mailroom. In effect, Aquaterra surmises that even if its bid package had been properly addressed and labeled, it still would have been mishandled here.
As a general rule, bidders are responsible for delivering their bids to the proper place at the proper time, and late delivery of a bid generally requires its rejection even if it is the lowest bid. J.C.N. Constr. Co., Inc., B-270068, B-270068.2,
While a late hand-carried bid may be considered if it is determined that the late receipt was due primarily to government mishandling after receipt at the government installation, a late bid should not be accepted if the bidder significantly contributed to the late receipt by not acting reasonably in fulfilling its own responsibility to submit its bid in a timely manner. Comspace Corp., B-281067,
The protest is denied.
Gary L. Kepplinger
General Counsel
[1]Amendment No. 2 to the solicitation notified all prospective bidders that the contracting specialist initially identified in the IFB would no longer be the point of contact for the procurement and identified another contracting specialist as the new point of contact.
[2] Aquaterra notes that the contracting division address is the only office location identified in the amended solicitation and that the post office box provided for bid submission is inapplicable to handcarried bids submitted by commercial carriers that require a street address for delivery.
[3] The agency reports that, since the firm had already ordered the required steel for the work, it only partially terminated the award in order to receive the ordered steel.
[4] To the extent the protester speculates that even if it had properly identified on its bid envelope that a bid was enclosed, the agency would have mishandled its bid, as it allegedly did for the other bid delivered late with Aquaterra's bid package (where that other bid was apparently marked with the solicitation number and bid opening information), we do not find Aquaterra's speculation in this regard persuasive as it provides no basis for us to question that Aquaterra's own actions were the paramount cause of its bid's late receipt. The protester's speculative surmise in this regard merely anticipates improper action by the agency on what would be a materially different set of facts than is present here. In any event, the argument fails to account for an additional defect in Aquaterra's bid submission, the firm's failure to address its bid package to the appropriate contact, which alone has been found to preclude a finding of government mishandling (i.e., even where a bid package is labeled with solicitation and bid opening information). See Comspace Corp., supra.