Cancellation of Contract Reward Due to Discrepancy Over Packaging Requirements

B-118428 Sep 21, 1954
Jump To:
Skip to Highlights

Highlights

The Secretary of the Air Force requested GAO?s opinion on whether or not it would be proper to accept delivery of a cleaning compound and pay the contractor on a quantum meriut basis out of fiscal year 1954 funds obligated on the original contract. A stop order was placed on the original contract upon receipt of a protest by the next lowest bidder; however, before receipt of the stop order, 90 percent of the cleaning compound had already been blended and stored.