Skip to main content

A-6138, APRIL 30, 1925, 4 COMP. GEN. 902

Skip to Highlights

Highlights

PAYMENT OF A VOUCHER AT THE FULL CONTRACT PRICE COVERING A DELAYED DELIVERY IS AUTHORIZED ONLY IF ACCOMPANIED BY A STATEMENT BY THE HEAD OF THE DEPARTMENT OF THE FACTS AS TO THE EXTENT AND CAUSE OF THE DELAY AND THAT IN HIS OPINION NO DAMAGES WERE SUSTAINED BY THE GOVERNMENT. THE PRESUMPTION IN CASES OF CONTRACTS LET BY COMPETITIVE BIDDING IS THAT THE GOVERNMENT IS GENERALLY DAMAGED BY DELAYS WHERE TIME IS OF THE ESSENCE OF THE CONTRACT. WITH REQUEST FOR DECISIONS AS TO WHETHER PAYMENT THEREON IS AUTHORIZED WITHOUT DEDUCTION OF LIQUIDATED DAMAGES FOR DELAY IN DELIVERY. THE CONTRACT UNDER WHICH DELIVERY WAS MADE CONTAINING A REVISED LIQUIDATED DAMAGE CLAUSE DIFFERING IN ITS TERMS FROM SIMILAR CONTRACTS.

View Decision

GAO Contacts

Shirley A. Jones
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries