Skip to main content

Matter of: Big River Construction Company File: B-250961 Date: October 26, 1992

B-250961 Oct 26, 1992
Jump To:
Skip to Highlights

Highlights

PROCUREMENT Sealed Bidding Bid guarantees Responsiveness Signatures Powers of attorney Protest of agency's rejection of bid as nonresponsive due to defective bid bond is dismissed where power of attorney form attached to the bond did not designate the individual who signed the bond as an attorney-in-fact authorized to bind the surety. The bid bond submitted with Big River's bid was properly executed. Was signed on behalf of the surety by Shirley R. As the bid thus failed to establish that the individual signing the bid bond was authorized to bind the surety. Ourada's general power of attorney is on file with the Corps. There was no question as to Ms. Big River concludes that its bid should have been considered responsive.

View Decision

Matter of: Big River Construction Company File: B-250961 Date: October 26, 1992

PROCUREMENT Sealed Bidding Bid guarantees Responsiveness Signatures Powers of attorney Protest of agency's rejection of bid as nonresponsive due to defective bid bond is dismissed where power of attorney form attached to the bond did not designate the individual who signed the bond as an attorney-in-fact authorized to bind the surety; bid thus failed to establish surety's ability to be bound under the solicitation.

Attorneys

DECISION

Big River Construction Company protests the rejection of its bid under invitation for bids (IFB) No. DACW45-92-B-0101, issued by the Army Corps of Engineers for work on the Boyer Chute Channel of the Missouri River. The Corps rejected Big River's bid because the surety's power of attorney form attached to the bid bond failed to designate the individual who signed the bond on behalf of the surety as an attorney-in-fact authorized
to bind the surety.

We dismiss the protest.

The IFB required the submission of a bid guarantee in the amount of 20
percent of the bid. Big River submitted the low bid. The bid bond
submitted with Big River's bid was properly executed, and was signed on
behalf of the surety by Shirley R. Ourada as attorney-in-fact. A
completed power of attorney form attached to the bond, however, listed a
Robert L. Reynoldson as the attorney-in-fact authorized to bind the
surety. As the bid thus failed to establish that the individual signing
the bid bond was authorized to bind the surety, the Corps rejected the bid
as nonresponsive.

Big River contends that its failure to provide a power of attorney form
for Ms. Ourada with its bid should be waived as a minor informality
because Ms. Ourada's general power of attorney is on file with the Corps;
consequently, there was no question as to Ms. Ourada's authority to bind
the surety. Big River concludes that its bid should have been considered
responsive.

Big River's argument fails to state a valid basis of protest. It is well
established that a bid bond is defective and renders the bid nonresponsive
if it is not clear that it will bind the surety. Techno Eng'g & Constr.,
Inc., B-243932, July 23, 1991, 91-2 CPD Para. 87. In this regard,
responsiveness of a bid--including the ability of the bid guarantee to
bind the surety under the IFB--must be evident from the face of the bid
documents. See id; Nova Group, Inc., B-220626, Jan. 23, 1986, 86-1 CPD
Para. 80. Even if the attorney-in-fact who signed Big River's bid bond
had actual authority to bind the surety, there was no evidence of this on
the face of the bid documents. As the enforceability of the bond against
the surety could not be determined from the bid documents themselves, the
Corps properly considered the bid bond to be defective, and the bid
therefore nonresponsive. See id.

The protest is dismissed.

GAO Contacts

Office of Public Affairs