B-215411.3, OCT 9, 1984, 84-2 CPD 391

B-215411.3 Oct 09, 1984
Jump To:
Skip to Highlights

Highlights

FILED WITH GAO MORE THAN 10 WORKING DAYS AFTER DECISION WAS ISSUED AND. IS DISMISSED AS UNTIMELY. CMCI'S PRESENT RECONSIDERATION REQUEST WAS FILED (RECEIVED) WITH OUR OFFICE ON SEPTEMBER 21. ONCE AGAIN CMCI ARGUES THAT ITS PROTEST FILED AFTER BID OPENING WAS NOT UNTIMELY BECAUSE IT DID NOT BECOME AWARE OF THE RESTRICTIVE NATURE OF THE SPECIFICATION UNTIL AFTER BID OPENING. WE SEE NO REASON WHY THE ALLEGEDLY RESTRICTIVE NATURE OF THE SPECIFICATIONS SHOULD NOT HAVE BEEN APPARENT PRIOR TO BID OPENING. CMCI'S REQUEST FOR RECONSIDERATION IS UNTIMELY. OUR BID PROTEST PROCEDURES REQUIRE THAT REQUESTS FOR RECONSIDERATION BE FILED WITH OUR OFFICE WITHIN 10 WORKING DAYS AFTER THE BASIS FOR RECONSIDERATION IS OR SHOULD HAVE BEEN KNOWN. 4 C.F.R.

View Decision

B-215411.3, OCT 9, 1984, 84-2 CPD 391

CONTRACTS - PROTESTS - GENERAL ACCOUNTING OFFICE PROCEDURES - RECONSIDERATION REQUESTS - TIMELINESS DIGEST: REQUEST FOR RECONSIDERATION OF PRIOR DECISION, FILED WITH GAO MORE THAN 10 WORKING DAYS AFTER DECISION WAS ISSUED AND, PRESUMABLY, RECEIVED BY THE PROTESTER, IS DISMISSED AS UNTIMELY.

CERTIFIED MECHANICAL CONTRACTORS, INC. - REQUEST FOR RECONSIDERATION

CERTIFIED MECHANICAL CONTRACTORS, INC. (CMCI), REQUESTS RECONSIDERATION OF OUR DECISION IN CERTIFIED MECHANICAL CONTRACTORS, INC. - REQUEST FOR RECONSIDERATION, B-215411.2, AUG. 20, 1984, 84-2 CPD PARA. 200, AFFIRMING OUR INITIAL DECISION IN CERTIFIED MECHANICAL CONTRACTORS, INC., B-215411, JUNE 20, 1984, 84-1 CPD PARA. 654, WHERE WE DISMISSED AS UNTIMELY CMCI'S PROTEST AGAINST ALLEGED SOLICITATION IMPROPRIETIES BECAUSE CMCI DID NOT PROTEST TO THE AGENCY OR GAO UNTIL AFTER BID OPENING. SEE 4 C.F.R. SEC. 21.2(B)(1) (1984); M & M SERVICES, INC., B-210818.2, MAR. 25, 1983, 83-1 CPD PARA. 308.

CMCI'S PRESENT RECONSIDERATION REQUEST WAS FILED (RECEIVED) WITH OUR OFFICE ON SEPTEMBER 21, 1984. ONCE AGAIN CMCI ARGUES THAT ITS PROTEST FILED AFTER BID OPENING WAS NOT UNTIMELY BECAUSE IT DID NOT BECOME AWARE OF THE RESTRICTIVE NATURE OF THE SPECIFICATION UNTIL AFTER BID OPENING. AS WE PREVIOUSLY POINTED OUT, WE SEE NO REASON WHY THE ALLEGEDLY RESTRICTIVE NATURE OF THE SPECIFICATIONS SHOULD NOT HAVE BEEN APPARENT PRIOR TO BID OPENING.

IN ANY EVENT, CMCI'S REQUEST FOR RECONSIDERATION IS UNTIMELY.

OUR BID PROTEST PROCEDURES REQUIRE THAT REQUESTS FOR RECONSIDERATION BE FILED WITH OUR OFFICE WITHIN 10 WORKING DAYS AFTER THE BASIS FOR RECONSIDERATION IS OR SHOULD HAVE BEEN KNOWN. 4 C.F.R. SEC. 21.9(B) (1984). CMCI'S REQUEST WAS FILED 23 WORKING DAYS AFTER ISSUANCE OF OUR AUGUST 20 DECISION. WE ASSUME THAT A PROTESTER WILL RECEIVED A DECISION NOT LATER THAN 1 CALENDAR WEEK AFTER ITS ISSUANCE. WINDWARD MOVING & STORAGE CO., INC. - RECONSIDERATION, B-213885.3, SEPT. 17, 1984, 84-2 CPD PARA. ???. SINCE THIS RECONSIDERATION REQUEST IS BASED ON DISAGREEMENT WITH OUR AUGUST 20 DECISION AND SINCE THE REQUEST WAS NOT FILED WITHIN THE 10-DAY PERIOD PROVIDED UNDER OUR BID PROTEST PROCEDURES, IT IS DISMISSED. SEE WINDWARD MOVING & STORAGE CO., INC. - RECONSIDERATION, B-213885.3, SUPRA.