B-196285, OCT 17, 1979

B-196285 Oct 17, 1979
Jump To:
Skip to Highlights

Highlights

DIGEST: DISPUTE REGARDING EQUITABLE PRICE ADJUSTMENT MUST BE PURSUED UNDER CONTRACT'S "DISPUTES" CLAUSE PROCEDURE AND THUS IS NOT FOR CONSIDERATION BY GAO. THE ADJUSTMENT WAS FIRST REQUESTED OF DFSC BY R.B.S. WHICH ARE ENTITLED "ECONOMIC PRICE ADJUSTMENT" AND "ECONOMIC PRICE ADJUSTMENT/FEDERAL COAL MINE HEALTH AND SAFETY ACT OF 1969. WHERE CERTAIN CONDITIONS ARE MET. IS CONCERNED THAT A "REASONABLE TIME" HAS PASSED WITHOUT ANY AGREEMENT BETWEEN THE PARTIES. ALTHOUGH IT IS NOT CLEAR FROM THE RECORD PRESENTED BY R.B.S. IT IS WELL ESTABLISHED THAT BOTH THE CONTRACTOR AND THE GOVERNMENT ARE BOUND TO FOLLOW AND EXHAUST THE ADMINISTRATIVE PROCEDURE SET OUT THEREIN FOR THE RESOLUTION OF DISPUTES.

View Decision

B-196285, OCT 17, 1979

DIGEST: DISPUTE REGARDING EQUITABLE PRICE ADJUSTMENT MUST BE PURSUED UNDER CONTRACT'S "DISPUTES" CLAUSE PROCEDURE AND THUS IS NOT FOR CONSIDERATION BY GAO.

R.B.S., INC.:

R.B.S., INC., REQUESTS OUR ASSISTANCE IN SECURING A PRICE ADJUSTMENT UNDER CONTRACT NO. DSA-76-D-0164 WITH THE DEFENSE FUEL SUPPLY CENTER (DFSC). THE ADJUSTMENT WAS FIRST REQUESTED OF DFSC BY R.B.S. APPROXIMATELY TWO YEARS AGO PURSUANT TO CLAUSES J28 AND J29 OF THE CONTRACT, WHICH ARE ENTITLED "ECONOMIC PRICE ADJUSTMENT" AND "ECONOMIC PRICE ADJUSTMENT/FEDERAL COAL MINE HEALTH AND SAFETY ACT OF 1969," RESPECTIVELY. THE CLAUSES PROVIDE FOR PRICE ADJUSTMENT, WHERE CERTAIN CONDITIONS ARE MET, WITHIN A "REASONABLE TIME" AFTER A REQUEST BY THE CONTRACTOR; R.B.S. IS CONCERNED THAT A "REASONABLE TIME" HAS PASSED WITHOUT ANY AGREEMENT BETWEEN THE PARTIES.

HOWEVER, EACH OF THE CITED CLAUSES ALSO PROVIDES THAT THE FAILURE OF THE PARTIES TO AGREE TO AN ADJUSTMENT "SHALL BE DEEMED A DISPUTE CONCERNING A QUESTION OF FACT WITHIN THE MEANING OF THE CLAUSE OF THIS CONTRACT ENTITLED 'DISPUTES'". ALTHOUGH IT IS NOT CLEAR FROM THE RECORD PRESENTED BY R.B.S. WHETHER THE FIRM HAS AS YET FORMALLY PROCEEDED UNDER THE CONTRACT'S "DISPUTES" CLAUSE, IT IS WELL ESTABLISHED THAT BOTH THE CONTRACTOR AND THE GOVERNMENT ARE BOUND TO FOLLOW AND EXHAUST THE ADMINISTRATIVE PROCEDURE SET OUT THEREIN FOR THE RESOLUTION OF DISPUTES, SEE HARRY C. PARTRIDGE, JR. & SONS, INC., B-191808, MAY 11, 1978, 78-1 CPD 366; THAT PROCEDURE PROVIDES FOR A DECISION BY THE CONTRACTING OFFICER, WITH THE CONTRACTOR HAVING THE RIGHT OF APPEAL FROM THE DECISION TO THE HEAD OF THE AGENCY CONCERNED.

FURTHERMORE, IT SHOULD BE NOTED THAT AS A RESULT OF THE UNITED STATES SUPREME COURT'S DECISION IN S&E CONTRACTORS, INC. V. UNITED STATES, 406 U.S. 1 (1972), OUR OFFICE NO LONGER REVIEWS DECISIONS UNDER THE "DISPUTES" CLAUSE ABSENT A SHOWING OF FRAUD OR BAD FAITH.

THE MATTER IS DISMISSED.