Skip to main content

B-228506, B-228865.2, Dec 3, 1987, 87-2 CPD 547

B-228506,B-228865.2 Dec 03, 1987
Jump To:
Skip to Highlights

Highlights

Properly was rejected as nonresponsive. The Navy rejected the bids as nonresponsive because each was executed by a stamped signature next to the typed name and title of the firm's president. There was no evidence with the bid that such execution was authorized. Porter notes that the bids did have the firm's corporate seal. That after bid opening it should have been clear to the Navy that Porter intended to be bound in each case. A bid that is not signed must be rejected as nonresponsive. If (1) the bid is accompanied by other signed documentation. There was no other signed material accompanying either bid (the bid bonds Porter furnished with its bids also were stamped). Porter does not argue that there was any pre- bid opening authorization for the stamped signatures.

View Decision

B-228506, B-228865.2, Dec 3, 1987, 87-2 CPD 547

PROCUREMENT - Sealed Bidding - Bid Guarantees - Responsiveness - Signatures - Authority DIGEST: Bid submission which included stamped signature for person authorized to sign but no authorization for such execution, or other signed documents referring to the bid, properly was rejected as nonresponsive.

Porter Contracting Co., Inc.:

Porter Contracting Co., Inc., protests the rejection of its bids under the Department of the Navy invitations for bids (IFB) Nos. N62477 87-B- 2006 and -2171, for fire protection services and certain construction services, respectively. The Navy rejected the bids as nonresponsive because each was executed by a stamped signature next to the typed name and title of the firm's president, and there was no evidence with the bid that such execution was authorized. Porter notes that the bids did have the firm's corporate seal, and that after bid opening it should have been clear to the Navy that Porter intended to be bound in each case. Porter argues that the failure to sign the bids therefore should be waived as minor informalities.

We deny the protests.

Generally, a bid that is not signed must be rejected as nonresponsive, because without an appropriate signature the offeror would not be bound upon the government's acceptance of the bid. The Commercial Siding & Maintenance Co., B-219764, Aug. 8, 1985, 85-2 CPD Para. 151. The failure to sign maybe waived as a minor informality, however, if (1) the bid is accompanied by other signed documentation, such as a bid bond or letter, which clearly refers to and identifies the bid itself, or (2) the bidder has formally adopted or authorized, before bid opening, the execution of documents by typewriter, printed, or stamped signature, and submits evidence of such authorization, and the bid carries such a signature. Federal Acquisition Regulation, 48 C.F.R. Sec. 14.405(c) (1986).

Neither of the stated exceptions applies here. There was no other signed material accompanying either bid (the bid bonds Porter furnished with its bids also were stamped), and Porter does not argue that there was any pre- bid opening authorization for the stamped signatures. The bids therefore properly were rejected. Moreover, Porter's post-bid opening actions and explanations are not relevant to the bid's acceptability. Permitting a bidder to correct its bid after bid opening on a matter that affects responsiveness would be prejudicial to other bidders because the firm would be gaining the advantage of deciding whether to accept or reject the award by making its bid responsive or not, as its business interest might dictate. National Investigation Bureau, Inc., B-191754, July 18, 1978, 78-2 CPD Para. 44.

Porter requests that it be awarded bid preparation costs. Since the firm's bids properly were rejected, however, the request is denied. See 4 C.F.R. Sec. 21.6(d) (1987).

The protests are denied.

GAO Contacts

Office of Public Affairs