[Protest of Army Corps of Engineers Rejection of Bid for Electrical Transformers]

B-283172.2 Published: Oct 04, 1999. Publicly Released: Oct 04, 1999.
Jump To:
Skip to Highlights

Highlights

A firm protested the Army Corps of Engineers' rejection of its bid for transformers, contending that the Corps improperly determined that its descriptive literature failed to address the solicitation's requirements. GAO held that the Corps properly rejected the protester's bid for transformers as nonresponsive, since the bid, which include information on two transformers, did not indicate which transformer would be furnished. Accordingly, the protest was denied.