[Protest of PCC Rejection of Bid for Turbidimeters]

B-245451 Published: Jan 02, 1992. Publicly Released: Jan 02, 1992.
Jump To:
Skip to Highlights

Highlights

A firm protested the Panama Canal Commission's rejection of its bid as nonresponsive for turbidimeters. GAO held that the protester's bid failed to establish that its product would meet all of the solicitation requirements. Accordingly, the protest was denied.

Office of Public Affairs

Topics

Bid rejection protestsBid responsivenessBrand name specificationsEquipment contractsFederal procurementSpecificationsDescriptive literatureBid evaluation protestsBidders