[Protest of Navy Contract Award for Tank Removal]

B-246114 Published: Oct 31, 1991. Publicly Released: Oct 31, 1991.
Jump To:
Skip to Highlights

Highlights

A firm protested a Navy contract award for tank removal, contending that the awardee's bid was nonresponsive, defective, and materially unbalanced. GAO held that the protester failed to provide a valid protest basis, since it failed to prove that the awardee's low bid limited, reduced, or modified the awardee's obligation to perform the contract in accordance with the solicitation criteria. Accordingly, the protest was dismissed.

Office of Public Affairs

Topics

Bid responsivenessContract award protestsNaval procurementQuestionable procurement chargesService contractsBid evaluation protestsBidder responsibilitySpecificationsU.S. NavySolicitationsIntellectual property rightsProtestsFuelsEnvironmental managementBid proposals