[Protest of Air Force Decision To Retain Function In House]

B-215407 Published: Jun 20, 1984. Publicly Released: Jun 20, 1984.
Jump To:
Skip to Highlights

Highlights

A firm protested the Air Force's decision not to contract for certain required services after a cost comparison. GAO held that the protest was untimely filed because it was not received by GAO within 10 days of the time the protester was notified that its protest to the Air Force was denied. Accordingly, the protest was denied.

Office of Public Affairs

Topics

Air Force procurementBid protestsComparative analysisCost analysisUntimely protestsU.S. Air ForceIntellectual property rightsFederal regulations