[Protest of FEMA Contract Award]
B-213332
Published: Mar 15, 1984. Publicly Released: Mar 15, 1984.
Skip to Highlights
Highlights
A firm protested a Federal Emergency Management Agency contract award, contending that the solicitation specifications were restrictive. Protesters are required to file their complaints with GAO within 10 days of their constructive knowledge that the protest was rejected by the procuring agency. GAO held that, since the protest was not filed within that period, it was untimely. Accordingly, the protest was dismissed.
Full Report
Office of Public Affairs
Topics
Contract award protestsUntimely protestsEmergency managementFederal regulationsSolicitation specificationsIntellectual property rights