A firm disagreed with a GAO decision and requested reconsideration of its protest. In its request for reconsideration, the protester stated that GAO failed to address a question concerning the reasonableness of its bid price. GAO stated that it will not consider a protest filed more than 10 working days after the protester received the decision. Accordingly, the request was dismissed.