Protest against Cancellation of Solicitation because of Ambiguous Specifications
B-192301
Published: Oct 02, 1978. Publicly Released: Oct 02, 1978.
Skip to Highlights
Highlights
A company protested cancellation of a solicitation because the Government contended that the specifications were ambiguous. The protester stated that the agency had used similar specifications in the past, and the specifications were not ambiguous or inadequate. The agency's requirements were not described properly, and the specifications were so inadequate and ambiguous that an award under them would not satisfy the Government's needs. The cancellation of the solicitation was proper.