Protest concerning Business Size Status and Bid Price
B-192075
Published: Aug 09, 1978. Publicly Released: Aug 09, 1978.
Skip to Highlights
Highlights
A company protested against award of a contract, alleging that: the bidder was not a small business concern, the low bidder could not perform at its bid price and thus its bid was nonresponsive, and acceptance of the low bid would result in additional costs in administering the contract. Size status is a matter for determination by the Small Business Administration rather than GAO. A bidder is not p