Protest to Contract Award Based on Ability of Competitors to Meet Specifications
B-189945
Published: Dec 20, 1977. Publicly Released: Dec 20, 1977.
Skip to Highlights
Highlights
Protesters to a contract award claimed that competitors could not meet the solicitation specifications. The protest against award to one of the firms was not considered since its bid had been withdrawn. Determinations of responsibility by an agency are not reviewed in the absence of fraud or misapplication of criteria; failure of the low bidder to comply with requirements was not demonstrated.