Protest against Solicitation Procedures

B-190702 Published: Dec 15, 1977. Publicly Released: Dec 15, 1977.
Jump To:
Skip to Highlights

Highlights

A company contended that as the only bidder on both schedules of a solicitation it should either be awarded a contract for both schedules or that all bids should be rejected and both schedules readvertised. The company also contended that if the limitation on funds prevented it from being considered for award of both schedules, then all of the bids for schedule 2 should have been rejected. The solicitation stated that bids would be considered for award on either or both of the schedules. It was apparent only after bid opening that the funding would be inadequate to support the award of both schedules; the agency's determination to consider only schedule 2 for award was proper. (SW)