Skip to main content

Request for Consideration of Late Proposal

B-188941 Aug 08, 1977
Jump To:
Skip to Highlights

Highlights

The protester objected to the determination that its late proposal could not be considered for award. The proposal, which was received two days after the closing date specified in the request for proposals, was properly rejected since the delay was attributable to the Postal Service rather than to mishandling at the Government installation. The offeror's allegedly superior experience and skills are not reasons to consider a late proposal.

Downloads

GAO Contacts

Office of Public Affairs