Appeal of Contract Termination
B-189164
Jun 15, 1977
Skip to Highlights
Highlights
The contractor protested the termination of two contracts for default and requested GAO to investigate the circumstances of the terminations. Disputes concerning the propriety of terminations for default are matters of contract administration, and are to be resolved by the contracting agency not by GAO. In addition, this matter was pending before the Armed Services Board of Contract Appeals, and therefore, GAO declined to consider it.