Protest Against Location of Contract Performance, Best and Final Notification, Proposal Revision, Type of Contract, and Evaluation Factors

B-187395 Published: Jun 08, 1977. Publicly Released: Jun 08, 1977.
Jump To:
Skip to Highlights

Highlights

A contract award for operations analysis and computer services was protested. The protest that all testing of computer software performance had to be performed onsite was denied; solicitation did not explicitly say so. An objection to the lack of a best and final notification was rejected. Despite an assertion to the contrary, the protester was informed and had an opportunity to revise the proposal. Challenges of firm-fixed-price type of contract and evaluation factors were untimely.

Full Report

Office of Public Affairs