Skip to main content

Rejection of Bid as Nonresponsive

B-184904 Dec 30, 1975
Jump To:
Skip to Highlights

Highlights

The protester objected to the rejection of its low bid as nonresponsive. While the invitation specified delivery within 280 days after date of award, the telegraphic bid offered delivery 280 days after receipt of award. Rejection of the bid as nonresponsive was proper since the bid effectively added the maximum number of days normally required for delivery of the award through the mails to the contract delivery period, thereby exceeding the required delivery schedule.

Downloads

GAO Contacts

Office of Public Affairs