Request for Price Adjustment Based on Mistake in Bid Discovered After Award
B-186959
Aug 30, 1976
Skip to Highlights
Highlights
A contractor requested an adjustment in the contract price based on a mistake in its bid discovered after award. The contracting officer requested verification of the bid price after noticing the disparity with other bids. Since the awardee was aware of the reason for the request for verification, the contract awarded after verification cannot be reformed.