A company protested award to any other firm, alleging that all other bidders were nonresponsive for lack of compliance with bid requirements. The company also protested the contracting officer's determination that it was not responsive to the solicitation. The agency agreed that all bids other than the protesters' were nonresponsive, so that protest was not considered. The protester's failure to submit a "Disclosure Statement" and appropriate certification did not render the bid nonresponsive since that requirement was not applicable to this procurement.