Responsiveness of Bid Based on Performing All Work Onsite at a Government Facility
B-192095
Dec 04, 1978
Skip to Highlights
Highlights
The protester objected to the rejection of its bid as nonresponsive. Even though the solicitation specification was unclear as to the portion of contract work which was to be performed onsite at the Government's facility, a bid which was conditioned on use of the Government facility for all of the contract work was properly rejected as nonresponsive. Due to the unclear provisions of the solicitation, the Government should determine whether the successful bidder included in its price costs for work which the agency intends to perform itself and should take appropriate remedial action.