Rejection of Bid as Nonresponsive

B-187033 Dec 17, 1976
Jump To:
Skip to Highlights

Highlights

Protester failed to provide any descriptive literature with bid in response to brand name or equal solicitation, but did after bid opening. Since agency could not tell from this literature whether bidder's product met requirements, bid was rejected as nonresponsive.