GAO’s recommendations database contains report recommendations that still need to be addressed. GAO’s priority recommendations are those that we believe warrant priority attention. We sent letters to the heads of key departments and agencies, urging them to continue focusing on these issues. Below you can search only priority recommendations, or search all recommendations.
Our recommendations help congressional and agency leaders prepare for appropriations and oversight activities, as well as help improve government operations. Moreover, when implemented, some of our priority recommendations can save large amounts of money, help Congress make decisions on major issues, and substantially improve or transform major government programs or agencies, among other benefits.
As of October 25, 2020, there are 4812 open recommendations, of which 473 are priority recommendations. Recommendations remain open until they are designated as Closed-implemented or Closed-not implemented.
Browse or Search Open Recommendations
Have a Question about a Recommendation?
- For questions about a specific recommendation, contact the person or office listed with the recommendation.
- For general information about recommendations, contact GAO's Audit Policy and Quality Assurance office at (202) 512-6100 or apqa@gao.gov.
Results:
Subject Term: Exploration
GAO-20-68, Dec 19, 2019
Phone: (202) 512-4841
including 1 priority recommendation
Agency: National Aeronautics and Space Administration
Status: Open
Comments: NASA agreed with this recommendation and stated that the Advanced Exploration Systems division will review program life-cycle review plans to ensure enterprise and program requirements are reconciled across the mission. NASA is in the process of determining the organizational structure of the Human Exploration and Operations Mission Directorate. Following this completion, NASA officials stated that the appropriate control board and division structures for review and program direction will become active.
Agency: National Aeronautics and Space Administration
Status: Open
Comments: NASA agreed with this recommendation and stated it would conduct a joint cost and schedule confidence level analysis or equivalent. The Gateway program is planning to conduct a series of project- and program-level reviews and assessments aligned with key decision point reviews. This includes conducting a joint cost and schedule confidence level analysis or equivalent of the Gateway initial configuration to support a program key decision point planned for fall 2021. NASA has not yet taken action on this recommendation.
Agency: National Aeronautics and Space Administration
Status: Open
Comments: NASA agreed with this recommendation, but has not yet taken action on it. NASA stated that it would provide a schedule for future reviews, including whether there will be a Key Decision Point (KDP) II, at the KDP-I review currently scheduled for fall 2021.
Agency: National Aeronautics and Space Administration
Status: Open
Priority recommendation
Comments: NASA agreed with the recommendation and stated that the agency will provide a preliminary cost estimate for the Artemis III mission by the end of 2020. Further, NASA stated that it will provide an updated cost estimate for the Artemis III mission after it establishes cost and schedule commitments for some of the projects that compose the lunar mission, currently planned for the Spring of 2021. To fully implement this recommendation, NASA will need to provide a cost estimate.
Agency: National Aeronautics and Space Administration
Status: Open
Comments: NASA agreed with this recommendation and stated that it is developing a document that will summarize the trades and architectural studies, but the document is not yet complete.
Agency: National Aeronautics and Space Administration
Status: Open
Comments: NASA agreed with this recommendation, but has not yet taken any action on it. NASA stated that it will provide additional clarifying guidance for conducting analyses of alternatives for new programs in the next update to NASA Procedural Requirements 7120.5E, "NASA Space Flight Program and Project Management Requirements." NASA plans to complete the update of the procedural requirement in September 2021.
GAO-20-28, Dec 10, 2019
Phone: (202) 512-4040
Agency: Department of Veterans Affairs: Office of the Secretary
Status: Open
Comments: In February and March 2020, VA's Vocational Rehabilitation & Employment (VR&E) conducted a consistency study of VR&E plan development. The study identified areas that warrant refresher training for counselors. VR&E plans to roll out this training to all counselors by August 2020. We will consider closing this recommendation when VR&E completes this effort.
GAO-19-436R, Sep 18, 2019
Phone: (202) 512-3841
Agency: Department of the Interior
Status: Open
Comments: In May 2020, BLM officials stated that they will revise the LR2000 Bond Review Report to identify all instances in which a state office needs to develop a corrective action plan in accordance with BLM policy. They estimate this will be completed by June 2021.
Agency: Department of Agriculture
Status: Open
Comments: As of July 2020, the agency has made progress in implementing this recommendation. Specifically, the agency has modified the bonding portion of the Natural Resource Manager data system to include required data fields to record the initial bond received, adjustments made to required bonding amount, and date of last annual review when a needed adjustment was determined. The agency has also added a remarks field to record any increase or decrease in the estimated cost of reclamation that resulted in the revised required bond amount. The agency is currently working to update its internal guidance so that staff are aware of the requirement and process to document these items. We agreed to check back on the status of that guidance in early 2021 and will update the recommendation status at that time.
GAO-19-377, Jun 19, 2019
Phone: (202) 512-4841
including 2 priority recommendations
Agency: National Aeronautics and Space Administration
Status: Open
Priority recommendation
Comments: NASA agreed with this recommendation. As of February 2020, NASA stated that it is conducting a rebaseline of the cost and schedule commitments for the SLS program and will document final decisions in an Agency Baseline Commitment decision memorandum. NASA officials anticipate they will complete this effort in Spring 2020. To fully implement this recommendation, NASA will need to measure cost growth using a baseline that reflects the scope of work currently planned for the first mission.
Agency: National Aeronautics and Space Administration
Status: Open
Priority recommendation
Comments: NASA partially agreed with this recommendation, stating that providing the estimate to the forecasted launch date rather than to the committed baseline date of April 2023 is the most appropriate approach. In November 2019, program officials told us that they will consider this recommendation as part of updating the joint confidence level analysis for the program's Key Decision Point D review. This review occurs before the program enters the system assembly, integration and test, and launch phase, and is not scheduled to occur until December 2020. To fully implement this recommendation, NASA needs to provide an updated cost estimate through April 2023.
Agency: National Aeronautics and Space Administration
Status: Open
Comments: NASA agreed with this recommendation and stated that the acquisition strategy for the second mobile launcher requires the use of 3D product modeling and that it will be the source for all engineering activities including integrated design reviews to demonstrate design maturity. It is too soon to assess the design maturity prior to construction start and we will provide updated information on actions NASA has taken at that time.
Agency: National Aeronautics and Space Administration
Status: Open
Comments: NASA agreed with the intent of this recommendation and stated that the SLS and Orion program offices reevaluate their strategies for incentivizing contract performance as part of normal contracting activities including contract restructures, contract baseline adjustments, and new contract actions. The Orion program has awarded a long term contract for production of the Orion spacecraft that incorporates new strategies intended to reduce contract costs. The SLS program is in the process of negotiating long term production contracts for required hardware.
GAO-18-476, Jul 11, 2018
Phone: (202) 512-4841
including 1 priority recommendation
Agency: National Aeronautics and Space Administration
Status: Open
Comments: NASA did not concur with our recommendation that the Commercial Crew Program should include the results of its schedule analysis in its quarterly reports to Congress. In July 2019, NASA reaffirmed that it will be working to ensure that the contractors' schedules and the program's internal assessments sync up as the program gets closer to launch, which is the process it used in March 2019 leading up to SpaceX's uncrewed test flight. GAO continues to believe that the recommendation is valid because the program's schedule risk analysis would provide Congress with valuable insight into potential delays, which are likely.
Agency: National Aeronautics and Space Administration
Status: Open
Priority recommendation
Comments: NASA agreed with this recommendation. NASA stated that it is in discussions with Russia to obtain additional seats on its Soyuz spacecraft for NASA crew as a contingency plan. NASA is also providing Extra-Vehicular Activity and robotics training for a subset of cosmonauts to support U.S. Operating Segment operations, and looking at a possible extension of the duration of the Space X Demonstration 2 crewed test flight. In November 2019, NASA reported that it completed its actions for this recommendation. However, while NASA is working on potential solutions, there is no contingency plan in place. To fully implement this recommendation, NASA needs to provide documentation of its contingency plan.
Agency: National Aeronautics and Space Administration
Status: Open
Comments: NASA partially concurred with our recommendation, stating it documented the agency's risk tolerance level with respect to loss of crew for the program in its May 2011 safety memo. NASA stated that ultimately the Commercial Crew Program is accountable for ensuring that the contractors' systems meet the loss of crew value of 1 in 270. In July 2019, the Commercial Crew Program noted that it will continue to determine its risk tolerance with respect to loss of crew and formally document its decisions at program management meetings. We continue to believe that, before agency certification, the key parties must collectively determine how the agency will determine its risk tolerance with response to loss of crew, as the risk tolerance for the loss of crew requirement depends on which entity is presenting the results of its analysis. We believe this approach will reduce confusion and increase transparency. In late September 2020, GAO received additional information from NASA on actions taken to implement this recommendation. We are currently assessing this information.
Agency: National Aeronautics and Space Administration
Status: Open
Comments: NASA concurred with our recommendation to document lessons learned related to the loss of crew requirement. In June 2020, NASA told us that they expect to take action to close this recommendation by the end of May 2021.
GAO-16-165, Jan 21, 2016
Phone: (202) 512-3841
Agency: Department of Agriculture
Status: Open
Comments: As of May 2020, the Forest Service said it has the statutory authority to issue a rule that establishes a fee structure, but it does not have the authority to collect and retain fees for hardrock mine plan processing activities. The Forest Service said it worked with the Department of Agriculture and Office of Management and Budget (OMB) to submit a request through the President's Budget for authority from Congress to retain any fees collected from mine operations. The President's Budget for fiscal year 2021, developed by OMB, included such a request to Congress. If Congress grants this authority, the Forest Service said it will issue a rule that establishes a fee structure for hardrock mine operations so it can begin retaining collected fees.
Agency: Department of the Interior
Status: Open
Comments: According to a letter received from the agency in April 2016, BLM expressed concern about whether promulgating a rule to assess cost recovery fees for environmental assessment would result in faster permitting times and noted that such an undertaking may be challenging to complete given resource limitation as a result of other high priority rule making efforts currently underway by BLM. The agency proposed conducting an internal analysis to determine whether requiring cost recovery would result in reduced permitting times and expected that report to be completed by the end of 2017. We contacted the Department of the Interior in April 2020 and it had no new information to provide at that time. We will update the status of this recommendation as more information becomes available.
GAO-15-562, Jul 23, 2015
Phone: (202) 512-2623
Agency: Department of the Interior
Status: Open
Comments: The Department of Interior's (DOI) Bureau of Land Management (BLM) agreed with our recommendation. In support of closing this recommendation, officials from BLM re-iterated their policy about sending updates regarding guidance changes, which is included in its directives handbook. They also provided us with an example of its timely communication to BLM employees to announce the issuance of its revised Fund Code Handbook. We reviewed the directives handbook and verified that it contains guidance for communicating policy and procedural changes affecting the mining law program's expenditure-related processes. While the guidance in the directives handbook is a good start towards meeting the intent of our recommendation, we communicated to BLM in fiscal year 2019 that the findings in the report were caused in part by inadequate communication processes and the accessibility of the guidance to staff. To address the recommendation, we would like to see evidence that BLM has established procedures to ensure proper communication of changes or policies to the staff using BLM guidance, which includes having written procedures on how BLM publishes updates or communicates policy information, where guidance should be published in BLM's internal page, and the BLM officials who are in charge of that process. In fiscal year 2020, we have sent additional follow-up questions to the agency and are currently waiting for a response. We will continue to monitor the agency's actions to address this recommendation.
GAO-14-385, May 8, 2014
Phone: (202) 512-4841
including 2 priority recommendations
Agency: National Aeronautics and Space Administration
Status: Open
Priority recommendation
Comments: NASA partially agreed with this recommendation, stating that it defined and documented life-cycle costs for SLS to a first demonstrated capability, consistent with cost estimating best practices and NASA project and program management policy and that it would report costs associated with the second exploration mission via its annual budget submission. In January 2020, NASA stated that it is evaluating changes to NASA Procedural Requirements 7120.5E, "NASA Space Flight Program and Project Management Requirements," to better enable the necessary insight into program affordability and efficient monitoring of total program costs and execution for multi-year, multi-cadence type programs. Further, NASA stated that it is investigating plans to redefine performance expectations for multi-decade programs' formal commitments while maintaining visibility to the entire plan. To address this recommendation, NASA needs to establish separate cost and schedule baselines for work required to support SLS for EM-2, which is now known as Artemis II.
Agency: National Aeronautics and Space Administration
Status: Open
Priority recommendation
Comments: NASA partially agreed with this recommendation, stating that it had established separate programs for SLS, Orion, and the ground systems and adopted a block upgrade approach for SLS. In January 2020, NASA stated that it plans to establish an agency baseline commitment for capability upgrades (e.g., Block 1B upgrades, such as Mobile Launcher-2 and Exploration Upper Stage) above the $250 million threshold. A joint confidence level analysis will be performed at key decision points and will include the cost and schedule range estimates for each of these upgrades. To address this recommendation, NASA needs to provide evidence that it established separate cost and schedule baselines for each additional SLS, Orion, and Ground Systems Development and Operations capability blocks that encompass all life-cycle costs, including operations and sustainment.
GAO-12-423, Jul 30, 2012
Phone: (202) 512-3841
including 1 priority recommendation
Agency: Department of the Interior
Status: Open
Priority recommendation
Comments: Interior has taken steps to identify and evaluate drilling risks, and its work is ongoing. For example, according to BSEE officials, BSEE's SafeOCS program is one effort through which data is collected on risk factors associated with drilling. BSEE expanded the SafeOCS program in 2016 to include required reporting of well control equipment and barrier failure incidents. Additionally, in 2017, BSEE completed two retrospective analyses of factors associating with risk, however, according to BSEE officials, both analyses were limited by the quality of the data. In December 2019, Interior officials stated that the Gulf of Mexico Region's Office of District Operations Support (DOS) has been developing an approach to apply a secondary review to drilling permits deemed to be "high risk." According to these officials, this secondary review will be performed by pre-selected subject matter experts, identified because of their experience with certain aspects of drilling operations. To determine what drilling permits should receive a secondary review, DOS explored a variety of approaches before settling on a two-prong method. Because efforts remain ongoing, it is too soon to assess the extent to which these efforts will be successful. Until such policies are fully implemented and shown to be effective, Interior may not be able to adjust and evaluate its oversight--including inspections--in a cost-effective manner.