Reports & Testimonies
Recommendations Database
GAO’s recommendations database contains report recommendations that still need to be addressed. GAO’s priority recommendations are those that we believe warrant priority attention. We sent letters to the heads of key departments and agencies, urging them to continue focusing on these issues. Below you can search only priority recommendations, or search all recommendations.
Our recommendations help congressional and agency leaders prepare for appropriations and oversight activities, as well as help improve government operations. Moreover, when implemented, some of our priority recommendations can save large amounts of money, help Congress make decisions on major issues, and substantially improve or transform major government programs or agencies, among other benefits.
As of October 25, 2020, there are 4812 open recommendations, of which 473 are priority recommendations. Recommendations remain open until they are designated as Closed-implemented or Closed-not implemented.
Browse or Search Open Recommendations
Have a Question about a Recommendation?
- For questions about a specific recommendation, contact the person or office listed with the recommendation.
- For general information about recommendations, contact GAO's Audit Policy and Quality Assurance office at (202) 512-6100 or apqa@gao.gov.
Results:
Subject Term: Energy
GAO-20-228, Dec 20, 2019
Phone: (202) 512-2834
Agency: General Services Administration: Office of the Administrator
Status: Open
Comments: As of April 2020, GSA indicated in its 180-day letter that it had published on its website draft guidance in response to the Federal Personal Property Management Act of 2018. In addition, GSA identified several actions it planned to take in the coming months, such as publishing a comprehensive plan and timelines to address GAO's recommendation, publishing a request for information in the Federal Register to seek comments and suggestions, and engaging additional subject matter experts and related associations and standards group to improve upon the draft guidance. GAO will continue to monitor GSA's efforts to implement this recommendation.
GAO-20-101, Dec 20, 2019
Phone: (202) 512-2834
Agency: Department of Agriculture
Status: Open
Comments: USDA concurred with this recommendation. As of April 2020, USDA's 180-day letter has not been received.
Agency: Department of Energy: Office of the Secretary
Status: Open
Comments: As of March 2020, DOE indicated in its 180-day letter that the agency concurred with the recommendation, and will update their annual personal property reporting requirements. DOE anticipates having this recommendation implemented by September 30, 2020. GAO will continue to monitor DOE's efforts to implement this recommendation.
Agency: Department of Labor: Office of the Secretary
Status: Open
Comments: As of February 2020, DOL indicated in its 180-day letter that they concurred with the recommendation, and have taken steps to improve the monitoring and oversight of Job Corps Property. This includes modifying the GSAXcess approval process by elevating review of all GSAXcess requests made by Job Corps Centers to DOL's Employment Training Administration's (ETA) national office. ETA is also working with DOL's Office of the Assistant Secretary for Administration and Management (OASAM) to develop a process for GSAXcess review that includes identifying approval levels for each category of property, identifying categories of property requiring additional review and approvals, and coordinating and streamlining access request procedures. These changes will be reflected in DOL's Office of Job Corps standard operating procedures (SOP), which is expected to be issued at the end of fiscal year 2020. DOL expects to provide training to Job Corps staff and Job Corps Centers in support of the SOP that will be provided annually. GAO will continue to monitor DOL's efforts to implement this recommendation.
Agency: Department of Agriculture
Status: Open
Comments: USDA concurred with this recommendation. As of April 2020, USDA's 180-day letter has not been received.
Agency: Department of Energy: Office of the Secretary
Status: Open
Comments: As of March 2020, DOE indicated in its 180-day letter that the agency concurred with the recommendation, and will update internal policies, and provide personal property information on DOE's internal informational website known as Powerpedia. DOE anticipates implementing this recommendation by September 30, 2020. GAO will continue to monitor DOE's efforts to implement this recommendation.
Agency: General Services Administration: Office of the Administrator
Status: Open
Comments: As of February 2020, GSA indicated in its 180-day letter that it concurred with the recommendation, and has taken steps to revise the Personal Property Reporting Tool (tool). GSA has added relevant authorities to the tool as recently as July 2019, and will continue to contact agencies to ensure relevant authorities are included in the tool. GSA is also evaluating technical updates to the tool to ensure that reporting agencies select an appropriate authority when reporting personal property. GSA plans to complete these actions by July 31, 2020, and inform agencies of these changes in their guidance by the end of fiscal year 2020. GAO will continue to monitor GSA's efforts to implement the recommendation.
Agency: General Services Administration: Office of the Administrator
Status: Open
Comments: As of February 2020, GSA indicated in its 180-day letter that it concurred with the recommendation. GSA will better communicate with agencies to better understand the confusion of reporting on loaned excess property, as reporting requirements are in statute, regulations, and guidance. GSA also plans to review and update by July 31, 2020, relevant regulations and guidance in this area including Federal Management Regulation Bulletin B-27, "Annual Executive Agency Reports on Excess and Exchange/Sale Personal Property." GAO will continue to monitor GSA's efforts to implement this recommendation.
GAO-20-63, Dec 17, 2019
Phone: (202) 512-3841
Agency: Department of Energy: Office of the Secretary
Status: Open
Comments: In June 2020, DOE officials told us that its Office of Environmental Management (EM) Portsmouth/Paducah Project Office (PPPO) is in the process of developing a program management master plan, to include site-integrated master schedules and life-cycle cost estimates, for the Portsmouth and Paducah gaseous diffusion plants (GDPs). Officials stated that the plan will incorporate program management leading practices as appropriate. According to DOE officials, EM will direct PPPO to use actual collected cost and schedule information for integration of relevant lessons learned from ETTP cleanup into integrated program plans, schedules, and estimates. DOE officials estimated that this effort would be completed by December 31, 2020.
Agency: Department of Energy: Office of the Secretary
Status: Open
Comments: In June 2020, DOE officials told us that its Office of Environmental Management (EM) is assessing and identifying an appropriate mechanism for tracking expenditures for both the Portsmouth and Paducah GDP sites, using a standardized approach with an Earned Value Management System (EVMS) reporting on, at a minimum, an annual basis. According to DOE officials, PPPO is in the process of using the ETTP data as a basis of comparison for contractor estimates and assessing the potential development of cost estimating tools for independent cost estimating. DOE officials estimated that this effort would be completed by December 31, 2020.
Agency: Department of Energy: Office of the Secretary
Status: Open
Comments: In June 2020, DOE officials told us that its Office of Environmental Management (EM) has directed the Portsmouth and Paducah GDP sites to review and incorporate the practices from GAO's Cost Estimating Guide (GAO-20-195G), as appropriate, into the next revision of each site's life-cycle cost baselines. According to DOE officials, Oak Ridge is in the process of procuring a follow-on cleanup contract, which includes the scope to complete the cleanup of ETTP. According to DOE officials, given that the cleanup of the ETTP GDP is nearly complete, the baseline for the entire ETTP GDP will not be included in the life cycle cost estimate review. Officials stated the remaining scope of work for the ETTP GDP will, however, become part of the performance baseline for the next Oak Ridge cleanup contractor. DOE officials estimated that this effort would be completed by December 31, 2020.
Agency: Department of Energy: Office of the Secretary
Status: Open
Comments: In June 2020, DOE officials told us that its Office of Environmental Management (EM) has incorporated the use of an independent facilitator on a case-by-case basis to help resolve any disagreements, in conjunction with the Environmental Protection Agency (EPA), and Kentucky and Tennessee state regulators over cleanup priorities, remedies, and cost estimation assumptions. Officials stated that most recently, the Paducah GDP site used an independent facilitator to resolve disagreements with EPA Region IV and Kentucky state regulators. According to DOE officials, in the future, EM will continue the use of an independent facilitator, as deemed appropriate. DOE officials estimated that this effort would be completed by December 31, 2020.
Agency: Department of Energy: Office of the Secretary
Status: Open
Comments: In June 2020, DOE officials told us that its Office of Environmental Management (EM) has prepared the triennial Uranium Enrichment Decontamination and Decommissioning Fund Report, providing accomplishments through fiscal year 2019 and disclosing the most recent environmental liability estimate associated with remaining challenges and scope of cleanup at the GDPs. Officials stated that the report is being circulated for approval. DOE officials estimated that this effort would be completed by December 31, 2020.
GAO-19-7, Feb 14, 2019
Phone: (202) 512-3841
Agency: Department of the Interior: Bureau of Land Management
Status: Open
Comments: In July 2019, BLM's Assistant Secretary for Land and Minerals Management wrote a letter to GAO stating that the bureau agreed that there are additional opportunities to improve the Inspection and Enforcement program's internal control reviews and that policies should be updated and widely circulated. Specifically, BLM wrote that by early August 2020, the bureau will issue updated guidance and procedures for conducting internal control reviews and that this guidance would take the form of a manual, handbook or Instruction Memorandum. BLM also wrote that it is establishing teams to conduct internal control reviews, monitoring the status of any past-due reviews and actively engaging across its multiple state offices to ensure timely resolution. In late August 2020, BLM's Audit Liaison Officer informed GAO that due to competing workload priorities and key management vacancies, BLM now plans to implement this recommendation by the end of June 2021.
Agency: Department of the Interior: Bureau of Land Management
Status: Open
Comments: In responding to our report, BLM stated that its July 2012 oversight policy, which expired in September 2013, should not have been allowed to lapse and given the importance of internal control reviews, the bureau will continue to use the July 2012 policy to conduct future reviews. In July 2019, BLM's Assistant Secretary for Land and Minerals Management wrote a letter to GAO stating that the bureau agreed that there are additional opportunities to improve the Inspection and Enforcement program's internal control reviews and that policies should be updated and widely circulated. In addition, BLM wrote that by early August 2020, the bureau will issue updated guidance and procedures for conducting internal control reviews and that this guidance would take the form of a manual, handbook, or Instruction Memorandum. In late August 2020. BLM's Audit Liaison Officer informed GAO that due to competing workload priorities and key management vacancies, BLM now plans to implement this recommendation by the end of June 2021.
Agency: Department of the Interior: Bureau of Land Management
Status: Open
Comments: In July 2019, BLM's Assistant Secretary for Land and Minerals Management wrote a letter to GAO stating that the bureau agreed that there are additional opportunities to improve the Inspection and Enforcement program's internal control reviews and that policies should be updated and widely circulated. Specifically, BLM wrote that by early August 2020, the bureau will issue updated guidance and procedures for conducting internal control reviews and that this guidance would take the form of a manual, handbook, or Instruction Memorandum. In addition, BLM noted that the guidance will help ensure that the bureau completes internal control reviews in a timely manner using a consistent risk-based approach. In late August 2020. BLM's Audit Liaison Officer informed GAO that due to competing workload priorities and key management vacancies, BLM now plans to implement this recommendation by the end of June 2021.
GAO-17-43, Nov 10, 2016
Phone: (202) 512-3841
Agency: Department of Energy
Status: Open
Comments: In June 2013, an executive order established the White House Council on Native American Affairs. However, the Council did not convene under the current Presidential administration until mid-2020. We will follow-up with DOE in fiscal year 2021 regarding this recommendation.
Agency: Department of the Interior
Status: Open
Comments: In June 2013, an executive order established the White House Council on Native American Affairs. The Tribal Energy Subgroup's efforts were to focus on creating a coordinated effort among the federal agencies to promote energy and energy infrastructure development in Indian Country. The Council convened under the current administration in mid-2020. We believe Interior should still pursue this collaboration and agreements with these agencies and will monitor the agency's progress.
Agency: Department of the Interior
Status: Open
Comments: In September 2019 BIA officials stated that they had begun to identify the critical skills and competencies necessary for select Indian energy-related occupations. BIA officials told us that, once complete, agency officials will be able to use the catalog of necessary skills and competencies to identify training needs for existing staff. To fully implement this recommendation, BIA needs to 1) assess the critical skills and competencies needed to fulfill BIA's responsibility related to energy development and 2) identify potential gaps. As of January 2020, BIA is in the early stages of identifying necessary skills and competencies, and BIA officials told us that they expect to complete the catalog of skills and competencies by the end of fiscal year 2020.
Agency: Department of the Interior
Status: Open
Comments: Our recommendation was based on our findings that the workforce composition of agency offices is not regularly reviewed to provide reasonable assurance that it is consistent with BIA's mission and individual tribes' priorities and goals. In December 2019, BIA officials told us that they were in the early stages of developing a process to regularly assess workforce composition at agency offices. BIA officials said that they drafted a data collection tool to collect workforce composition information, and that BIA would be developing a system to collect and analyze the data on an annual basis. According to BIA officials, BIA intends to use the workforce composition data to identify BIA's staffing needs and inform BIA budget requests. BIA officials said that they aim to complete the documented process for assessing workforce composition by the end of February 2020.
GAO-15-331, Mar 23, 2015
Phone: (202) 512-3841
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA believes it has met the requirements of the recommendation and considers it closed. In our March 2015 report--which examined NNSA's report on the contract to manage and operate the Pantex Plant and the Y-12 National Security Complex under a single management and operating (M&O) contract with Consolidated Nuclear Services (CNS)--we recommended that NNSA enhance the clarity and completeness of its future reports on the costs and benefits of M&O contract competitions. While NNSA demonstrated progress in implementing this recommendation in its September 2017, August 2018, and April 2019 reports to Congress on the costs and benefits of the contract competitions for the Sandia, Nevada, and Los Alamos sites respectively, NNSA did not provide clear and complete information on all required elements of these reports. Specifically, for the Sandia National Laboratories M&O contract, in our August 2018 report we found that NNSA addressed most but not all reporting requirements. For example, NNSA's report addressed all requirements pertaining to cost savings, other benefits, and disruptions or delays, but only partially addressed the reporting requirements on the limitations or uncertainties about cost savings and on the immediate costs of competition and over the life of the contract. NNSA issued a report in August 2018 on the costs and benefits of its competition of the M&O contract for the Nevada National Security Site. In our April 2019 report on NNSA's cost-benefit analysis of that contract competition, we found that, of the five required reporting elements, NNSA's report addressed one with detail but addressed the other four without detail. In April 2019 NNSA issued its cost-benefit analysis of the competition for the Los Alamos National Laboratory contract. In our January 2020 report on NNSA's cost-benefit report for that contract competition, we found that it addressed five reporting elements on costs and disruption during contract transition with detail, partially addressed two reporting elements on uncertainties and benefits, and did not address one reporting element on activities to be covered by the M&O contractor. Since our 2015 recommendation, NNSA's cost-benefit reports on M&O contract competitions have generally provided clearer and more complete information on most of the required reporting elements, but they have not provided clear and complete information on all required reporting elements. In June 2020, NNSA announced that it would end the current CNS contract for Pantex and Y-12 management and operations instead of awarding the contractor its final option term. This will result in a new contract competition and award by the end of the current contract's term on September 30, 2021. The NNSA report on the costs and benefits of that competition may give us another opportunity to assess the quality of NNSA's reports for clarity and completeness on the required reporting elements.