GAO’s recommendations database contains report recommendations that still need to be addressed. GAO’s priority recommendations are those that we believe warrant priority attention. We sent letters to the heads of key departments and agencies, urging them to continue focusing on these issues. Below you can search only priority recommendations, or search all recommendations.
Our recommendations help congressional and agency leaders prepare for appropriations and oversight activities, as well as help improve government operations. Moreover, when implemented, some of our priority recommendations can save large amounts of money, help Congress make decisions on major issues, and substantially improve or transform major government programs or agencies, among other benefits.
As of October 25, 2020, there are 4812 open recommendations, of which 473 are priority recommendations. Recommendations remain open until they are designated as Closed-implemented or Closed-not implemented.
Browse or Search Open Recommendations
Have a Question about a Recommendation?
- For questions about a specific recommendation, contact the person or office listed with the recommendation.
- For general information about recommendations, contact GAO's Audit Policy and Quality Assurance office at (202) 512-6100 or apqa@gao.gov.
Results:
Subject Term: "Naval procurement"
GAO-20-370, May 11, 2020
Phone: (202) 512-4841
Agency: Department of Defense: Department of the Navy
Status: Open
Comments: The Department of the Navy concurred with our recommendation in May 2020, stating that it would establish an analysis plan for evaluating Other Procurement, Navy-funded pilot program availabilities. In July 2020, the Director, Maintenance & Modernization, within the Office of the Deputy Assistant Secretary of the Navy for Ship Programs, stated that the Navy has drafted this analysis plan, which is now undergoing required Department of Defense (DOD) reviews. The Director stated that he expects this review process to be completed sometime in late summer 2020. Once complete, he stated that his office will provide the analysis plan to GAO for review to confirm that it satisfies our recommendation.
GAO-19-497, Apr 8, 2019
Phone: (202) 512-4841
Agency: Department of Defense: Department of the Navy
Status: Open
Comments: DOD concurred with this recommendation, stating that the Columbia Class Program cost estimate will be updated in 2019 to support the lead ship authorization Decision Acquisition Board in 2020. As of September 2020, we have yet to receive an update on the status of this recommendation.
Agency: Department of Defense: Department of the Navy
Status: Open
Comments: DOD agreed with this recommendation, stating that the updated Columbia Class Program cost estimate would incorporate estimated savings from use of the authorities associated with the fund and savings associated with the Columbia lead submarine cost estimate. In August 2020, Navy officials indicated that NAVSEA updated the Columbia lead submarine cost estimate to include updates to the estimate of savings from the use of the authorities associated with the Fund.
Agency: Department of Defense: Department of the Navy
Status: Open
Comments: DOD concurred with this recommendation, stating that the lead submarine cost estimate and cost risk analysis will be updated to support the lead ship authorization Decision Acquisition Board in 2020. In August 2020, Navy officials indicated that NAVSEA updated the Columbia lead submarine cost estimate. However, this estimate was completed after funding was requested for lead submarine construction. While the Office of Cost Assessment and Program Evaluation plans to conduct an assessment of this estimate in the summer of 2020, the assessment will also be too late to inform the Navy's funding request.
GAO-17-418, Jul 13, 2017
Phone: (202) 512-4841
including 1 priority recommendation
Agency: Department of Defense
Status: Open
Priority recommendation
Comments: DOD disagreed with our recommendation to clarify the Navy's ship delivery policy and stated that other existing policies help ensure the completion and capability of ships at delivery. However, as of August 2020, Navy officials stated that they are working on a new response based on ongoing discussions with GAO and they expect to develop a new proposal for responding to this recommendation by December 2020. We maintain that the Navy's ship delivery policy is a key instruction for ensuring that complete, mission-capable ships are provided to the fleet and should be revised in line with our recommendation.
Agency: Department of Defense
Status: Open
Comments: DOD and the Navy did not concur with this recommendation, noting that the current timing of Navy Board of Inspection and Survey (INSURV) trials provides the Navy with an opportunity to ensure contractual obligations have been met and identify construction deficiencies for correction during the post-delivery period. DOD and the Navy also stated that adding another INSURV trial at the end of the post-delivery period would not be cost-effective and could delay ship deployment schedules. However, we found that most of the significant construction deficiencies identified prior to delivery were not corrected until the post-delivery period and, therefore, INSURV generally did not have an opportunity to inspect these corrections before ships were provided to the fleet. Given this, we maintain that the Navy should re-assess the timing of its post-delivery trials in support of INSURV's responsibility to make recommendations for fleet introduction. As of August 2020, DOD officials stated that they are working on a proposal to address this recommendation based on ongoing discussions with GAO and they expect to complete this proposal by December 2020.
Agency: Department of Defense
Status: Open
Comments: DOD partially concurred with this recommendation. DOD and the Navy agreed to report obligation work limiting dates (OWLD) in its Selected Acquisition Reports to Congress, and, as of December 2018, has implemented this portion of the recommendation. The department added the OWLDs for all ships that have yet to achieve this milestone to its Selected Acquisition Reports and plans to continue reporting this information in all subsequent Selected Acquisition Reports. However, DOD did not agree to report ready-to-deploy dates in the Selected Acquisition Reports to Congress, noting that operational factors outside of acquisition concerns can affect the timing of this milestone. While we agree that readiness to deploy is a fleet determination, we continue to believe that this date is important for Congressional oversight, as it remains the best milestone for determining when a ship has achieved a sufficient level of completeness to operate, under the Navy's current framework for ship delivery. As of August 2020, DOD and Navy officials stated that they are working on a new proposal for addressing the recommendation based on ongoing discussions with GAO and they expect to complete this proposal by December 2020.
GAO-17-575, Jun 13, 2017
Phone: (202) 512-4841
including 1 priority recommendation
Agency: Department of Defense
Status: Open
Priority recommendation
Comments: In its comments on our draft report DOD disagreed with our recommendation, stating that it currently provides progress reports to Congress on costs for CVN 78 and CVN 79. In July 2020, Navy officials stated that the department continues to disagree with this recommendation. We continue to maintain that Selected Acquisition Reports represent the primary statutorily required means for DOD to report on program status. Grouping average unit costs for all Ford-class ships obscures individual ship cost growth and does not provide Congress with an adequate level of insight to monitor this over $55 billion program. Our recommendation would ensure that Congress receives insight into the costs of each existing and planned Ford-class ship. To fully implement this recommendation, the report should include cost information on individual ships.
GAO-16-71, Mar 3, 2016
Phone: (202) 512-4841
including 1 priority recommendation
Agency: Department of Defense
Status: Open
Priority recommendation
Comments: DOD partially concurred with this recommendation in February 2016 by committing to study policy changes with regard to warranties, but disagreed that additional cost data were needed to inform these decisions, and questioned whether warranties are suitable for ship acquisitions. In February 2017, a Navy-funded study found that the Navy had no policy to collect data, and that the little data available were not useful for determining when warranties are suitable. In response to the study, the Navy agreed that, by December 2017, it would make some policy and contractual changes to collect data, but it continued to maintain that warranties are likely not suitable for ship contracts. In January 2018, the Navy issued guidance to help contracting officers determine when and how to use a warranty or guarantee, but the Navy has collected only one warranty cost proposal from one shipbuilder for a contract for a single ship and, going forward, Navy officials stated that they do not have plans to systematically collect such data. In August 2019, we recommended in GAO-19-512 that the Navy collect warranty pricing on its new class of frigates, as the Navy initially did not include warranty pricing as part of its request for proposals for the ship class. However, as of August 2020, the Navy has not made meaningful efforts to gain pricing data for warranties and has stated that the department does not plan to take any further action. To fully implement this recommendation, the Navy needs to collect additional data in order to determine cases in which warranties could contribute to improvements in the cost and quality of Navy ships.