GAO’s recommendations database contains report recommendations that still need to be addressed. GAO’s priority recommendations are those that we believe warrant priority attention. We sent letters to the heads of key departments and agencies, urging them to continue focusing on these issues. Below you can search only priority recommendations, or search all recommendations.
Our recommendations help congressional and agency leaders prepare for appropriations and oversight activities, as well as help improve government operations. Moreover, when implemented, some of our priority recommendations can save large amounts of money, help Congress make decisions on major issues, and substantially improve or transform major government programs or agencies, among other benefits.
As of October 25, 2020, there are 4812 open recommendations, of which 473 are priority recommendations. Recommendations remain open until they are designated as Closed-implemented or Closed-not implemented.
Browse or Search Open Recommendations
Have a Question about a Recommendation?
- For questions about a specific recommendation, contact the person or office listed with the recommendation.
- For general information about recommendations, contact GAO's Audit Policy and Quality Assurance office at (202) 512-6100 or apqa@gao.gov.
Results:
Federal Agency: "Department of Energy: National Nuclear Security Administration"
GAO-20-703, Sep 9, 2020
Phone: (202) 512-3841
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
GAO-20-409, Jul 24, 2020
Phone: (202) 512-3841
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
GAO-20-451, Jun 24, 2020
Phone: (202) 512-3841
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA concurred with the recommendation. In comments on a draft of the report, DOE stated that NPO plans to work with CNS on a plan for the remaining reinvestment funds, with an estimated completion date of December 31, 2020.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA concurred, in principle, with the recommendation. In its comments on a draft of the report, NNSA stated that potential benefits of the cost savings program should be considered for future contracts, as applicable. NNSA stated that it believes this recommendation is closed with actions to address other recommendations. We disagree and continue to believe that NNSA should document an analysis of the cost savings program, including its cost effectiveness, to determine the exportability of the program to other contracts.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA concurred with the recommendation. In its comments on a draft of the report, NNSA stated that it plans to upload lessons learned into DOE's Corporate Lessons Learned Database so they can be considered by other sites by December 31, 2020.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA concurred with the recommendation. In its comments on a draft of the report, NNSA stated that it plans to evaluate whether to expand use of Annual Controlled Baselines to other sites by December 31, 2020.
GAO-20-357, Jun 9, 2020
Phone: (202) 512-3841
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: In a May 2020 letter signed by the NNSA Administrator that provided agency comments on our draft report, NNSA neither agreed nor disagreed with our recommendation. However, NNSA stated that by December 2020 the agency plans to complete a strategic management plan that will more clearly articulate the integration of management controls for the various components of its microelectronics activities. NNSA stated that it believes this action is consistent with our recommendation. We are encouraged by this planned action and will evaluate the completed strategic management plan to determine if it meets the intent of our recommendation.
GAO-20-180, Jan 16, 2020
Phone: (202) 512-3841
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA agreed with the recommendation and officials said they are working to establish a work breakdown structure change control process by June 30, 2020.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA agreed with the recommendation and plans to review how management and operating (M&O) contractors make manual changes to their financial data as part of an ongoing review of M&O contractors indirect cost data. The review is expected to be completed by September 30, 2020.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA agreed with the recommendation and plans to establish a process to verify that the management and operating (M&O) contractors are crosswalking their financial data to the appropriate NNSA work breakdown structure by September 30, 2020. As of April 2020, NNSA has hired two federal employees who will be conducting site visits to work with M&O contractors on verifying their crosswalks.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA agreed with the recommendation and plans to establish a process to verify that the management and operating (M&O) contractors are consistently applying common cost element definitions at their sites and across the nuclear security enterprise by September 30, 2020. As of April 2020, NNSA has hired two federal employees who will be conducting site visits to work with M&O contractors on verifying their crosswalks.
GAO-19-608, Sep 26, 2019
Phone: (202) 512-3841
including 1 priority recommendation
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA concurred with our recommendation and agreed to update its methodology for the fiscal year 2021 budget justification materials in an effort to ensure that contracts are counted accurately. Based on our review of the contracts listed in the budget justification materials, NNSA inappropriately excluded six contracts from its fiscal year 2021 congressional budget justification reporting. GAO is following up with NNSA officials to determine why these contracts were excluded.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA concurred in principle with the recommendation and planned to meet with congressional staff to discuss ways to further enhance the reported data before the 2021 budget materials were prepared. NNSA provided additional information in its fiscal year 2021 budget justification explaining that it did not have access to the information needed to report information to report required data regarding the number of FTE contractor personnel employed under an support service contract for more than 2 years. We will continue to follow-up on NNSA's progress in collecting and reporting the required data.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA concurred with the recommendation and included in the fiscal year 2021 budget justification materials additional information on the fund value and description in the table of support service contracts. However, NNSA did not total the amounts for each appropriation account. As a result, information on the total amounts of each appropriation account is not as transparent as it could be to assist Congress for planning purposes. GAO is following up with agency officials to identify any additional actions planned to close the recommendation.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: In its comments on a draft of this report, NNSA stated that it considers the recommendation closed based on processes already in place, as well as the complementary activities discussed in response to our sixth recommendation. We continue to believe that documenting planned oversight activities in the contract files is important to ensure that planned oversight is consistent throughout the duration of the contract. We will continue to monitor NNSA's implementation of this recommendation.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Priority recommendation
Comments: NNSA generally agreed with the recommendation. NNSA stated that, among other things, it will review and revise, as necessary, the designation letters for contractor officers' representatives to ensure they clearly address the expectations for daily operational awareness and monitoring for risks associated with high-risk contracts, including those involving activities closely associated with inherently governmental functions. We will continue to monitor the status of this recommendation.
GAO-19-449, Jun 17, 2019
Phone: (202) 512-3841
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: As of July 2020, we are currently reviewing agency information and plan to reach out as needed for additional information for this recommendation.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: Based on trade press reports, NNSA appears to be taking several actions that, collectively, may serve to close this recommendation as implemented. As of July 2020, we are awaiting information from agency officials and will update the status of this recommendation when the information is received.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: Based on trade press reports, NNSA appears to be making progress implementing this recommendation. As of July 2020, we have requested additional information from agency officials and will update the recommendation status when the information is received.
GAO-19-5, Feb 26, 2019
Phone: (202) 512-3841
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: The National Nuclear Security Administration (NNSA) concurred with the recommendation. In February 2020, NNSA issued its fiscal year 2020 Corporate Performance Evaluation Process Annual Implementation Guidance. This guidance included a new section specifying the process for collecting contractor performance information and further details regarding the preparation of interim feedback reports and final performance evaluation reports. However, the guidance is unclear regarding how this information can be traced to rating determinations. In order to provide more transparency and ensure this traceability, NNSA guidance and the Performance Evaluation Reports themselves should more clearly link how collected performance information tracks to rating determinations.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: The National Nuclear Security Administration (NNSA) concurred with the recommendation. In February 2020, NNSA issued its fiscal year 2020 Corporate Performance Evaluation Process Annual Implementation Guidance. This guidance provides instructions regarding the evaluation of cost performance, including examples of the types of cost information that should be collected and how cost data should be analyzed and described. However, the guidance's template for Performance Evaluation and Measurement Plans does not include any explicit cost performance Objectives or Key Outcomes and it is unclear how the cost performance information discussed in the guidance would enable an overall assessment of Management and Operating contractor cost performance. In order to provide quality cost information that does enable such an overall assessment, NNSA should clarify its guidance regarding cost performance information and how this information links to overall Management and Operating contractor performance.
GAO-19-101, Jan 31, 2019
Phone: (202) 512-3841
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: As of August 2020, NNSA provided a project plan for tasks to be completed for common financial reporting through 2021. However, NNSA has not developed requirements that define specific or detailed requirements for successful implementation of common financial reporting, such as the types of information that program managers need.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: As of August 2020, NNSA established a detailed project schedule for the common financial reporting effort through fiscal year 2021. However, NNSA should communicate this detailed project schedule for the effort to Congress on an annual basis.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: In June 2020, NNSA developed a risk management plan for common financial reporting which established a framework for identifying and managing risks. GAO will continue to monitor NNSA's efforts to implement the plan, including how NNSA identifies and documents risks and mitigates risk exposure using its management plan.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: As of September 2020, NNSA has continued to engage on a regular basis with its M&O contractors. However, similar efforts have not continued with stakeholders of the program offices.
GAO-19-49, Nov 13, 2018
Phone: (202) 512-4456
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA agreed with this recommendation and plans to develop relevant policies and procedures by June 2020. We will continue to monitor the agency's progress towards implementing our recommendation.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA agreed with this recommendation and plans to develop relevant policies and procedures by June 2020. We will continue to monitor the agency's progress towards implementing our recommendation.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA agreed with this recommendation and plans to develop relevant policies and procedures by June 2020. We will continue to monitor the agency's progress towards implementing our recommendation.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA agreed with this recommendation and plans to develop relevant policies and procedures by June 2020. We will continue to monitor the agency's progress towards implementing our recommendation.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA agreed with this recommendation and plans to develop relevant policies and procedures by June 2020. We will continue to monitor the agency's progress towards implementing our recommendation.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA agreed with this recommendation and plans to develop relevant policies and procedures by June 2020. We will continue to monitor the agency's progress towards implementing our recommendation.
GAO-18-246R, Aug 1, 2018
Phone: (202) 512-3841
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA agreed with this recommendation. Per NNSA, as of October 2018, it was developing a plan and schedule for implementing Procurement Management Reviews (PMRs), which will include monitoring how NNSA field offices manage older management and operating contract documents and use the results to improve access to such documents. As of April 2020, we will continue to monitor how NNSA carries out its oversight of field offices contract document management practices.
GAO-18-126, Feb 16, 2018
Phone: (202) 512-3841
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA disagreed with our recommendation and has not taken steps to implement it. In August 2019, GAO requested an update on the status of the small centrifuge project at Oak Ridge since NNSA officials indicated in May 2019 that the status of the small centrifuge project will impact NNSA's ability to complete the analysis of alternatives (AOA) process by December 2019, as originally planned. Early in calendar year 2020, NNSA announced that completion of the AOA would be delayed to the end of fiscal year 2020. In September 2020, NNSA stated that the COVID-19 pandemic had further delayed the AOA and that the agency had not determined a revised target date for completion. We will continue monitoring the AOA process and will review the AOA once it is completed to determine whether we can close this recommendation at that time.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA disagreed with our recommendation and has not taken steps to implement it. In August 2019, GAO requested an update on the status of the small centrifuge project at Oak Ridge since NNSA officials indicated in May 2019 that the status of the small centrifuge project will impact NNSA's ability to complete the analysis of alternatives (AOA) process by December 2019, as originally planned. Early in calendar year 2020, NNSA announced that completion of the AOA would be delayed to the end of fiscal year 2020. In September 2020, NNSA stated that the COVID-19 pandemic had further delayed the AOA and that the agency had not determined a revised target date for completion. We will continue monitoring the AOA process and will review the AOA once it is completed to determine whether we can close this recommendation at that time.
GAO-18-129, Jan 30, 2018
Phone: (202) 512-3841
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: In October 2018, NNSA stated that the integrated baseline reviews, internal reviews of earned value management (EVM) systems used by life extension programs (LEP), and other controls over data integration provide a practical and cost-beneficial approach to the validation of contractor EVM systems. However, in early 2019, NNSA conducted a lessons learned study to more fully assess the cost, benefit, mission impacts, and feasibility of implementing our recommendation for possible application to future LEPs. According to NNSA documentation, based on the results of the lessons learned study, NNSA concluded that the effort and expense needed to validate contractor EVM systems against the EVM national standard could be better used providing resources to improve the agency's ability to establish work breakdown structures, schedules, and integration of scope, cost, and schedule. As a result, as of September 2019, NNSA stated that its actions meet the intent of our recommendation. We disagree. As we stated in our report, without requiring an independent entity to validate that contractor EVM systems meet the EVM national standard, NNSA may not have assurance that its LEPs are obtaining reliable EVM data for managing their programs and reporting their status. We will continue to monitor NNSA's activities to address this recommendation.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: In October 2018, NNSA stated that it conducts ongoing surveillance through integrated baseline reviews, internal reviews of EVM systems used by LEPs, and other assessments, which consider national standards. However, in early 2019, NNSA conducted a lessons learned study to more fully assess the cost, benefit, mission impacts, and feasibility of implementing our recommendation for possible application to future LEPs. According to NNSA documentation, based on the results of the lessons learned study, NNSA concluded that the effort and expense needed to conduct surveillance reviews of contractor EVM systems to ensure compliance with the EVM national standard could be better used providing resources to improve the agency's ability to establish work breakdown structures, schedules, and integration of scope, cost, and schedule. As a result, as of September 2019, NNSA stated that its actions meet the intent of our recommendation. We disagree. As we stated in our report, without requiring an independent entity to conduct surveillance reviews of contractor EVM systems through program completion, NNSA may not have assurance that its LEPs are obtaining reliable EVM data for managing their programs and reporting their status. We will continue to monitor NNSA's activities to address this recommendation.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: In October 2018, NNSA stated that it has already incorporated specific benchmarks for technology readiness levels at decision points. As an example, it stated that it recommends a technology readiness level of 5 at the beginning of phase 6.3 for an LEP. As a result, NNSA stated that its actions meet the intent of our recommendation. We disagree. As we stated in our report, it is important for NNSA to establish a requirement, not just a recommendation, that LEP critical technologies meet specific technology readiness level benchmarks at decision points. We will continue to monitor NNSA's activities to address this recommendation.
GAO-17-341, Apr 26, 2017
Phone: (202) 512-3841
including 1 priority recommendation
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Priority recommendation
Comments: NNSA included a new section in the Fiscal Year 2020 Stockpile Stewardship and Management Plan (SSMP) of its analysis of the affordability of its weapons modernization plans. However, this section still does not include details about, or an assessment of, the options NNSA might have to take in the future--such as adjusting the schedules or scopes of certain programs or projects--to address an apparent misalignment between the future budget estimates of its portfolio of nuclear modernization programs and the projections of potential future budgets. Therefore, we will continue to review future SSMPs to assess whether NNSA has included additional information or an assessment consistent with this recommendation.
GAO-15-216, May 22, 2015
Phone: (202) 512-3841
including 1 priority recommendation
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Priority recommendation
Comments: We recommended that NNSA establish comprehensive policies and guidance, beyond a general framework, for using information from contractor assurance systems (CAS) to conduct oversight of management and operating (M&O) contractors, clarifying whether CAS is to cover mission-related activities and describing how to conduct assessments of risk, CAS maturity, and the level of the contractor's past performance. NNSA agreed with the recommendation and has taken an important step to revise its policy. However, NNSA needs to take additional action. Specifically, NNSA approved a revised corporate site governance policy in August 2016, and NNSA further revised its policy in October 2019. The revised policy improves on the agency's prior policy by clarifying one element in our recommendation that CAS is to cover mission-related activities. However the policy is still a general framework and NNSA has not established associated implementing guidance. Specifically, NNSA needs to develop guidance for NNSA headquarters' and field offices' procedures to use information from CAS and appropriately balance use of information from CAS with other more direct activities to oversee M&O contractors. As of April 2020, this recommendation remains open.
GAO-15-331, Mar 23, 2015
Phone: (202) 512-3841
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA believes it has met the requirements of the recommendation and considers it closed. In our March 2015 report--which examined NNSA's report on the contract to manage and operate the Pantex Plant and the Y-12 National Security Complex under a single management and operating (M&O) contract with Consolidated Nuclear Services (CNS)--we recommended that NNSA enhance the clarity and completeness of its future reports on the costs and benefits of M&O contract competitions. While NNSA demonstrated progress in implementing this recommendation in its September 2017, August 2018, and April 2019 reports to Congress on the costs and benefits of the contract competitions for the Sandia, Nevada, and Los Alamos sites respectively, NNSA did not provide clear and complete information on all required elements of these reports. Specifically, for the Sandia National Laboratories M&O contract, in our August 2018 report we found that NNSA addressed most but not all reporting requirements. For example, NNSA's report addressed all requirements pertaining to cost savings, other benefits, and disruptions or delays, but only partially addressed the reporting requirements on the limitations or uncertainties about cost savings and on the immediate costs of competition and over the life of the contract. NNSA issued a report in August 2018 on the costs and benefits of its competition of the M&O contract for the Nevada National Security Site. In our April 2019 report on NNSA's cost-benefit analysis of that contract competition, we found that, of the five required reporting elements, NNSA's report addressed one with detail but addressed the other four without detail. In April 2019 NNSA issued its cost-benefit analysis of the competition for the Los Alamos National Laboratory contract. In our January 2020 report on NNSA's cost-benefit report for that contract competition, we found that it addressed five reporting elements on costs and disruption during contract transition with detail, partially addressed two reporting elements on uncertainties and benefits, and did not address one reporting element on activities to be covered by the M&O contractor. Since our 2015 recommendation, NNSA's cost-benefit reports on M&O contract competitions have generally provided clearer and more complete information on most of the required reporting elements, but they have not provided clear and complete information on all required reporting elements. In June 2020, NNSA announced that it would end the current CNS contract for Pantex and Y-12 management and operations instead of awarding the contractor its final option term. This will result in a new contract competition and award by the end of the current contract's term on September 30, 2021. The NNSA report on the costs and benefits of that competition may give us another opportunity to assess the quality of NNSA's reports for clarity and completeness on the required reporting elements.
GAO-10-582, Jun 21, 2010
Phone: (202)512-6870
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA has significantly improved its work breakdown structure for Stockpile Services. The work breakdown structure now reflects a product or capability basis to a much greater extent than it did previously. NNSA restructured its budget starting with its fiscal year 2021 budget justification materials. GAO, through ongoing work, is continuing to monitor NNSA's development of cost estimates for Stockpile Services products and capabilities that inform future years' budget requests and justifications.
GAO-09-385, Mar 2, 2009
Phone: (202) 512-3000
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: In past and ongoing work, GAO has identified areas where NNSA's modernization plans may not align with planned funding requests over the Future Years Nuclear Security Plan (FYNSP) and post-FYNSP periods. Based on the FY 2014 Stockpile Stewardship and Management Plan (SSMP), (GAO-14-45) NNSA plans to work on five life extension programs (LEP) or major alterations through 2038. The FY 2014 SSMP states that the LEP workload represents a resource and production throughput challenge that requires improvements in LEP planning and execution. GAO's analysis indicates there is limited contingency time built into the LEP schedules, all of which are technically ambitious. Any delays in schedules could lead to an increase in program costs or a reduction in the number built for any of the LEPs, both of which have occurred in prior and ongoing LEPs. While NNSA has acknowledged issues and identified some steps to improve the LEP process, this recommendation will remain open and unimplemented until NNSA demonstrates successful LEP and refurbishment execution. We reconfirmed this finding in GAO-17-341 where we found the following: In some cases, NNSA's FY 2017 nuclear security budget materials do not align with the agency's modernization plans, both within the 5-year FYNSP for fiscal years 2017 through 2021 and beyond, raising concerns about the affordability of NNSA's planned portfolio of modernization programs. As of June 2020, this situation has not been fully addressed as evidenced by cost increases and likely delays in the B61-12 and W88 ALTV programs; an aggressive schedule in the W80-4 program, and a large scope in the W87-1 warhead replacement. In addition, new programs contained in the 2018 Nuclear Posture Review and the announcement of a new development effort, the W93, may further stress NNSA's program.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: A number of Stockpile Stewardship and Management Plans (SSMP) state that the life extension program (LEP) workload represents a resource and production throughput challenge that requires improvements in LEP planning and execution. The officials elaborated that the main area that will be strained is pit production. NNSA's plutonium strategy needs to be resourced fully and implemented successfully by 2030 to support the W87 warhead replacement. Additionally, the officials said that the UPF project and an arrange of associated programmatic efforts need to be operational by 2025 or there will be challenges in completing all of the planned LEPs. In addition, NNSA needs to re-establish depleted uranium operations, construct a new lithium facility and establish a domestic uranium enrichment function for tritium production by the late 2020s to meet stockpile needs. As such, this recommendation remains open and, given the aggressive warhead and bomb modernization efforts proceeding in parallel with infrastructure modernization efforts, will likely remain open for some time.
Agency: Department of Energy: National Nuclear Security Administration
Status: Open
Comments: NNSA has generally improved its management of construction projects, to include requirements setting, Analysis of Alternatives, and independent cost estimates, among other items. However, it is too soon to tell if these positive developments will help--or hinder--LEPs that are underway or are being conducted. Key uranium activities, to include construction and operating funds will not be complete until 2025; key tritium and lithium programs and facilities will not complete until the 2030s; key plutonium activities are underway as well, but will not be complete until the late 2020s. As of June 2020, there are no significant changes related to this recommendation, and it will continue to remain open.