GAO-08-475T:
Published: Feb 7, 2008
Publicly Released: Feb 7, 2008
Since the November 14, 2007, CVC hearing, the project's construction has progressed, and AOC is still anticipating an early November 2008 opening date. But risks to the project's schedule remain in several time-critical activities, especially fire alarm acceptance testing, which, under the current schedule, must be completed on time for the CVC to open on time. Delays in work on the East Front, t