Skip to main content

Hanford Cleanup: DOE Should Take Actions to Improve Inspections and Oversight of Contaminated Excess Facilities

GAO-20-161 Published: Jan 21, 2020. Publicly Released: Feb 20, 2020.
Jump To:

Fast Facts

Nuclear facilities that are no longer used await cleanup at the Department of Energy’s site in Hanford, WA. Contractors inspect and maintain these facilities, but DOE hasn’t ensured that these activities fully meet requirements. For example, structural conditions are unknown in parts of a facility that inspectors haven’t entered in 50 years.

In 2017, workers found a partial roof collapse in a storage tunnel. DOE evaluated physical causes, but did not examine all inspection and maintenance practices that may have contributed to the accident. We recommended doing so and taking steps to improve inspections and maintenance.

Hanford Plutonium Uranium Extraction Plant (PUREX) and Storage Tunnels

Aerial view of plant

Aerial view of plant

Skip to Highlights

Highlights

What GAO Found

The Department of Energy (DOE) has taken some actions to evaluate the physical causes that contributed to the May 2017 partial collapse of the Plutonium Uranium Extraction (PUREX) Tunnel 1, but has not determined the programmatic causes that led to the collapse, such as by completing an accident investigation or a root cause analysis, among other things. For example, although an engineering evaluation of the tunnels was completed at the request of the State of Washington, Richland Operations Office (RL) officials told GAO an accident investigation was not initiated because the event did not meet threshold requirements in a DOE order that includes, among other things, damages or costs exceeding $2.5 million. However, GAO's analysis shows that the costs of responding to the event and stabilizing the tunnel were about $10 million. At the contractor's request, RL also waived performance of a root cause analysis, which DOE guidance states is typically required for such a significant event, and agreed to a less rigorous analysis of the potential physical causes of the event. By conducting a root cause analysis to determine any programmatic weaknesses that contributed to the collapse of PUREX Tunnel 1, and taking action to address any identified weaknesses, DOE will have greater assurance that another, similar event will not take place.  According to a DOE report and GAO's review, although the Hanford contractor is generally conducting routine surveillance inspections of contaminated excess facilities, these inspections have weaknesses and GAO found that DOE has not ensured requirements are fully met. Specifically, DOE orders require that processes be in place to ensure that inspections are conducted to detect deterioration and determine whether the structural integrity of facilities is threatened. A December 2017 DOE report and GAO's review found that the surveillance and maintenance (S&M) inspections at several facilities were not comprehensive and that there are areas of some facilities that personnel infrequently or never enter—physically or by remote means—to conduct inspections. For example, parts of the Reduction-Oxidation Facility have not been entered in more than 50 years and structural conditions are unknown. Without conducting comprehensive inspections, RL cannot ensure that it is meeting all of DOE's S&M requirements, such as addressing aging degradation and obsolescence of some facilities, and preventing other potential events similar to the PUREX tunnel collapse.

In addition, GAO's review of oversight reports since 2013 by DOE headquarters offices responsible for evaluating field office operations found that none of these assessments focused on RL's management and oversight of the contractor's S&M activities. DOE's Oversight Policy requires DOE to conduct independent oversight to the extent necessary to evaluate the effectiveness of DOE field office oversight of contractor activities. Without conducting periodic assessments or audits focused on RL's management and oversight of the contractor's S&M activities for contaminated excess facilities, DOE does not have assurance that RL is overseeing S&M activity in a way that ensures these facilities are inspected and maintained in a safe and compliant condition pending final cleanup.

Why GAO Did This Study

DOE's Hanford site in Washington State contains thousands of contaminated excess facilities and waste sites that remain to be cleaned up. In May 2017, a partial roof collapse at a waste storage tunnel facility for one of the former plutonium nuclear processing plants raised questions about the S&M of Hanford's excess facilities and how RL prioritizes cleanup of these facilities.

GAO was asked to review DOE's cleanup of Hanford's contaminated excess facilities, including how DOE ensures that the Hanford Site contractor inspects and maintains facilities. This report examines, among other things, (1) DOE's actions to evaluate the causes of the PUREX tunnel collapse, and (2) the extent to which DOE ensures that S&M of Hanford's contaminate excess facilities meet DOE requirements.

GAO reviewed DOE documents, administered a questionnaire to collect S&M information about 18 selected facilities representing the majority of the Hanford facilities cleanup effort, conducted in-depth reviews of selected Hanford facilities, and interviewed DOE and Hanford cleanup contractor officials.

Recommendations

GAO recommends that DOE (1) analyze the programmatic root causes of the tunnel collapse, (2) routinely conduct comprehensive inspections of contaminated excess facilities and take timely action as warranted, and (3) assess RL oversight of S&M of Hanford excess facilities. DOE agreed with GAO's recommendations and stated that it is taking steps to implement all of them by December 2020.

Recommendations for Executive Action

Agency Affected Recommendation Status Sort descending
Office of the Assistant Secretary for Environmental Management The Assistant Secretary of DOE's Office of Environmental Management should direct RL to conduct a root cause analysis to identify any programmatic causes that may have led to the collapse of PUREX Tunnel 1. (Recommendation 1)
Open
DOE concurs with this recommendation and has agreed to conduct a root cause analysis examining the programmatic cause leading to the Hanford PUREX tunnel collapse. In DOE's October 2020 Audit Report regarding the implementation of recommendations in our report, DOE states that the Office of Environmental Management is taking action to implement this recommendation, but that action is still insufficient to satisfy the recommendation. As of April 21, 2023, DOE has yet to take action to fully address this recommendation.
Office of the Secretary of the Department of Energy The Secretary of Energy should ensure DOE headquarters offices responsible for the oversight of EM sites' field offices conduct an assessment of RL's management and oversight of the Hanford Site contractor's surveillance and maintenance activity for contaminated excess facilities. Based on the results of this assessment, DOE headquarters offices should consider whether such assessments should be conducted on a periodic basis. (Recommendation 3)
Closed – Implemented
DOE concurs with this recommendation and the Office of Environmental Management agreed to conduct an assessment, in coordination with headquarters oversight offices, of the Richland Operations Office's management and oversight of the Hanford Site contractor's surveillance and maintenance activities for contaminated excess facilities. In DOE's October 2020 Audit Report regarding the implementation of recommendations in our report, DOE states that the Office of Environmental Management is taking action to implement this recommendation, but that action is still insufficient to satisfy the recommendation. At the end of July 2021, DOE reported that it has taken action to implement this recommendation. However, due to safety and health work protocol and travel restrictions imposed in response to the COVID-19 pandemic, in August 2022, DOE reported that it had yet to complete assessment activities to ensure that actions take to address this recommendations were fully implemented. DOE was scheduled to complete action to fully address this recommendation by September 30, 2022. In November 2022, provided a report documenting that a DOE headquarters office has completed periodic assessments of their Richland Operations Office management and oversight of the Hanford Site contractor's surveillance and maintenance activity for contaminated excess facilities.
Office of the Assistant Secretary for Environmental Management The Assistant Secretary of DOE's Office of Environmental Management, while ensuring the protection of DOE workers, the public, and the environment, should ensure that RL directs the Hanford Site cleanup contractor to explore using robotic or other means to routinely complete comprehensive surveillance inspections of contaminated excess facilities to identify aging degradation and obsolescence of facilities and take timely action as warranted. (Recommendation 2)
Closed – Implemented
According DOE's October 2020 Audit Report regarding the implementation of recommendations in our report, DOE's Office of Environmental Management has implemented this recommendation. This report states that DOE's Office of Environmental Management provided additional direction to the Hanford Site cleanup contractor to continue to explore and use robotic or other means to routinely complete comprehensive surveillance inspections of contaminated excess facilities to identify aging degradation and obsolescence of facilities and take timely action as warranted. This report further states that this direction is documented in an Office of Environmental Management memo issued to the Hanford Site cleanup contractor.

Full Report

GAO Contacts

Office of Public Affairs

Topics

PlutoniumRoot cause analysisAccident investigationsUraniumRadioactive wastesEnvironmental managementNuclear facilitiesSoil contaminationEnvironmental liabilitiesNuclear waste