[Protest Against Navy Rejection of Bid for Laboratory Renovation]
B-227982
Published: Sep 14, 1987. Publicly Released: Sep 14, 1987.
Skip to Highlights
Highlights
A firm protested the Navy's rejection of its nonresponsive bid for laboratory renovation, contending that the Navy should allow it to correct a defect in its bid bond, since its bid was low. GAO held that the protester did not show that its surety had consented to alterations in its bid bond. Accordingly, the protest was denied.