Pursuant to a congressional request, GAO discussed the Air Force's F-22 aircraft development and procurement program.
GAO noted that: (1) in March 1999 GAO reported that it was unlikely the Air Force would be able to keep the F-22 engineering and manufacturing development (EMD) program, as planned, within the cost limit established by Congress; (2) in addition, GAO expressed concern about the significant reduction the Air Force had made in the testing it planned to complete before awarding contracts to initiate advance procurement to accelerate F-22 production; (3) both authorization and appropriations acts for fiscal year 2000 establish further congressional direction for the F-22 program; (4) the authorization act required certification by the Secretary of Defense, prior to beginning low-rate initial production, that the EMD test plan is adequate for determining F-22 operational effectiveness and suitability; (5) the appropriations act did not approve the beginning of F-22 low-rate initial production but approved funding for acquisition of additional flight-test aircraft with research, development, test, and evaluation funding; (6) the F-22 program has made progress in manufacturing and testing aircraft; (7) however, there continues to be several important issues regarding the cost of the EMD and production programs and the schedules for completion of EMD activities leading to production of F-22s in higher quantities; (8) preliminary indications from GAO's ongoing review of the EMD program's status show that, compared to the program's status in March 1999, sufficient cost reductions have not been implemented to ensure that EMD activities, as planned, can be completed within the cost limitation, and completion dates for testing F-22 aircraft may be further delayed; (9) GAO's evaluation of the Air Force's progress in meeting cost, schedule, and performance goals is continuing as directed in the National Defense Authorization Act for Fiscal Year 1998; (10) GAO plans to issue a report to Congress concerning its current evaluation by March 15, 2000; (11) in 1997, the Air Force indicated that the most probable cost for production of 438 F-22 aircraft would exceed its cost estimate by $13 billion; and (12) the Air Force plans to implement initiatives to offset this projected cost increase.
Jan 14, 2021
-
Columbia Class Submarine:
Delivery Hinges on Timely and Quality Materials from an Atrophied Supplier BaseGAO-21-257: Published: Jan 14, 2021. Publicly Released: Jan 14, 2021. -
Department of Defense:
Actions Needed to Improve Accounting of Intradepartmental TransactionsGAO-21-84: Published: Jan 14, 2021. Publicly Released: Jan 14, 2021.
Jan 12, 2021
-
DOD Critical Technologies:
Plans for Communicating, Assessing, and Overseeing Protection Efforts Should Be CompletedGAO-21-158: Published: Jan 12, 2021. Publicly Released: Jan 12, 2021.
Dec 10, 2020
-
Climate Resilience:
DOD Coordinates with Communities, but Needs to Assess the Performance of Related Grant ProgramsGAO-21-46: Published: Dec 10, 2020. Publicly Released: Dec 10, 2020. -
Electromagnetic Spectrum Operations:
DOD Needs to Address Governance and Oversight Issues to Help Ensure SuperiorityGAO-21-64: Published: Dec 10, 2020. Publicly Released: Dec 10, 2020.
Dec 2, 2020
-
Navy and Marine Corps:
Services Continue Efforts to Rebuild Readiness, but Recovery Will Take Years and Sustained Management AttentionGAO-21-225T: Published: Dec 2, 2020. Publicly Released: Dec 2, 2020.
Nov 20, 2020
-
GAO Audits Involving DOD:
Status of Efforts to Schedule and Hold Timely Entrance ConferencesGAO-21-185R: Published: Nov 20, 2020. Publicly Released: Nov 20, 2020.
Nov 19, 2020
-
Defense Acquisitions:
Joint Cyber Warfighting Architecture Would Benefit from Defined Goals and GovernanceGAO-21-68: Published: Nov 19, 2020. Publicly Released: Nov 19, 2020. -
Defense Intelligence:
Comprehensive Plan Needed to Improve Stakeholder Engagement in the Development of New Military Intelligence SystemGAO-21-57: Published: Nov 19, 2020. Publicly Released: Nov 19, 2020. -
Defense Production Act:
Opportunities Exist to Increase Transparency and Identify Future Actions to Mitigate Medical Supply Chain Issues:GAO-21-108: Published: Nov 19, 2020. Publicly Released: Nov 19, 2020.
Looking for more? Browse all our products here