Nuclear Health and Safety:
Corrective Actions on Tiger Teams' Findings Progressing Slower Than Planned
RCED-93-66: Published: Mar 25, 1993. Publicly Released: Apr 28, 1993.
Additional Materials:
- Full Report:
Contact:
Pursuant to a congressional request, GAO reviewed the Department of Energy's (DOE) compliance with environment, safety, and health (ES&H) regulations, focusing on: (1) the status of tiger team and follow-on progress assessments; and (2) DOE facilities' responsiveness in correcting identified problems.
GAO found that: (1) as of January 1993, the Secretary of Energy has approved corrective action plans for 30 of the 35 DOE facilities assessed by tiger teams; (2) as of March 31, 1992, 23 DOE facilities had completed 40 percent of the planned corrective actions, but progress was slower than anticipated; (3) the facilities' failure to meet their corrective action plan milestones is due to inadequate resources, overly optimistic schedules, and revised work plans; (4) some DOE facilities lack procedures for verifying corrective actions; (5) DOE has verified and closed about 64 percent of completed corrective actions and returned 126 cases to the contractors for further action; (6) DOE offices did not always independently verify the corrective action that they were responsible for; (7) DOE could not determine the effect of ES&H compliance on contractor award fees, since performance criteria were highly subjective; (8) DOE issued guidance in July 1990 that all performance evaluation plans should include corrective action performance, but field offices are not uniformly implementing the guidance; and (9) DOE has developed databases and workshops to share information on ES&H compliance, but not all facilities use the information effectively.
Dec 10, 2020
-
Uranium Management:
Actions to Mitigate Risks to Domestic Supply Chain Could Be Better Planned and CoordinatedGAO-21-28: Published: Dec 10, 2020. Publicly Released: Dec 10, 2020.
Dec 8, 2020
-
Offshore Wind Energy:
Planned Projects May Lead to Construction of New Vessels in the U.S., but Industry Has Made Few Decisions amid UncertaintiesGAO-21-153: Published: Dec 8, 2020. Publicly Released: Dec 8, 2020.
Nov 19, 2020
-
Nuclear Waste Disposal:
Better Planning Needed to Avoid Potential Disruptions at Waste Isolation Pilot PlantGAO-21-48: Published: Nov 19, 2020. Publicly Released: Nov 19, 2020.
Oct 29, 2020
-
Nuclear Safety:
DOE and the Safety Board Should Collaborate to Develop a Written Agreement to Enhance OversightGAO-21-141: Published: Oct 29, 2020. Publicly Released: Oct 29, 2020.
Oct 15, 2020
-
Nuclear Weapons:
NNSA Plans to Modernize Critical Depleted Uranium Capabilities and Improve Program ManagementGAO-21-16: Published: Oct 15, 2020. Publicly Released: Oct 15, 2020.
Jul 24, 2020
-
Nuclear Weapons:
Action Needed to Address the W80-4 Warhead Program's Schedule ConstraintsGAO-20-409: Published: Jul 24, 2020. Publicly Released: Jul 24, 2020.
Jun 24, 2020
-
National Nuclear Security Administration:
Analyzing Cost Savings Program Could Result in Wider Use and Additional Contractor EfficienciesGAO-20-451: Published: Jun 24, 2020. Publicly Released: Jun 24, 2020.
Jun 9, 2020
-
Nuclear Weapons:
NNSA Needs to Incorporate Additional Management Controls Over Its Microelectronics ActivitiesGAO-20-357: Published: Jun 9, 2020. Publicly Released: Jun 9, 2020.
May 13, 2020
-
Environmental Liabilities:
DOE Needs to Better Plan for Post-Cleanup Challenges Facing SitesGAO-20-373: Published: May 13, 2020. Publicly Released: May 13, 2020.
May 12, 2020
-
Hanford Waste Treatment Plant:
DOE Is Pursuing Pretreatment Alternatives, but Its Strategy Is Unclear While Costs Continue to RiseGAO-20-363: Published: May 12, 2020. Publicly Released: May 12, 2020.
Looking for more? Browse all our products here