New Denver Airport Followup

RCED-92-285R: Published: Sep 14, 1992. Publicly Released: Sep 14, 1992.

Additional Materials:


Office of Public Affairs
(202) 512-4800

GAO reviewed the construction schedule and cost status of the Denver International Airport. GAO found that: (1) as of July 1992, construction was on schedule, with 41 percent completed; (2) as of August 1992, the total cost was estimated to be $4 billion; (3) although costs of 27 contracts cited in its September 1991 report have increased about 5 percent due to change orders, the contracts remained about $89 million under their budgeted amount; (4) 83 percent of needed funds for the airport will come from unsecured revenue bonds, with the rest from federal grants, and passenger fees and excess revenues from Stapleton International Airport; (5) two of the four largest all-cargo carriers have decided to operate at the new airport rather than a smaller airport after officials relocated the cargo facilities at the new airport; (6) future cargo losses to the smaller airport could reduce revenues to the new airport, and increase fees to other users; and (7) expansion of the smaller airport for cargo operations would require greater federal expenditures, could potentially cause greater environmental impacts, and could delay flights at the new airport.

Feb 28, 2018

Jan 30, 2018

Jan 16, 2018

Dec 21, 2017

Dec 14, 2017

Dec 4, 2017

Nov 30, 2017

Nov 15, 2017

Nov 2, 2017

Oct 31, 2017

Looking for more? Browse all our products here