Mass Transit Grants: Development Time Frames for Selected UMTA Projects
RCED-91-184FS
Published: Jul 11, 1991. Publicly Released: Jul 11, 1991.
Skip to Highlights
Highlights
Pursuant to a congressional request, GAO provided information on the amount of time it took state and local agencies to complete the Urban Mass Transportation Administration's (UMTA) project development process, focusing on the differences between the established time frames and the actual processing times for 10 projects.
Full Report
Office of Public Affairs
Topics
Discretionary grantsFederal aid for transportationGrant award proceduresMass transitPlanningRoad constructionTransportationUrban development programsUrban planningUrban transportation