Capital Cost Associated With the Trunkline Liquefied Natural Gas Lake Charles Facility
RCED-83-237: Published: Aug 31, 1983. Publicly Released: Oct 19, 1983.
Additional Materials:
- Full Report:
Contact:
In response to a congressional request, GAO reviewed costs associated with the liquefied natural gas (LNG) facility constructed near Lake Charles, Louisiana.
The cost of constructing the LNG facility was about $589 million, an increase of about 258 percent over the estimate approved by the Federal Power Commission in 1977. The construction company reported that these cost increases were due to modifications of the plant design to ensure safety, efficiency, and compliance with State and Federal regulations, as well as labor problems and general inflation. When the first regular LNG shipments were received in December 1982, the cost had increased about 129 percent over estimated costs. Negotiations with the Algerian LNG supplier resulted in a renegotiated price for July through September 1983 and a 40-percent reduction in purchased quantities for April 1983 through November 1984. GAO noted that any adjustments will have a significant effect on the delivered price of natural gas. The Federal Energy Regulatory Commission (FERC) regulates the setting of rates that interstate pipelines charge their customers and has been active in negotiations with the supplier. FERC has monitored cost overruns, is conducting an ongoing audit of all costs associated with the facility, and has expressed concerns about project expenditures. GAO noted that FERC can exclude unreasonable costs from the base rate and order the construction and management company to refund the excess payments.
Dec 10, 2020
-
Uranium Management:
Actions to Mitigate Risks to Domestic Supply Chain Could Be Better Planned and CoordinatedGAO-21-28: Published: Dec 10, 2020. Publicly Released: Dec 10, 2020.
Dec 8, 2020
-
Offshore Wind Energy:
Planned Projects May Lead to Construction of New Vessels in the U.S., but Industry Has Made Few Decisions amid UncertaintiesGAO-21-153: Published: Dec 8, 2020. Publicly Released: Dec 8, 2020.
Nov 19, 2020
-
Nuclear Waste Disposal:
Better Planning Needed to Avoid Potential Disruptions at Waste Isolation Pilot PlantGAO-21-48: Published: Nov 19, 2020. Publicly Released: Nov 19, 2020.
Oct 29, 2020
-
Nuclear Safety:
DOE and the Safety Board Should Collaborate to Develop a Written Agreement to Enhance OversightGAO-21-141: Published: Oct 29, 2020. Publicly Released: Oct 29, 2020.
Oct 15, 2020
-
Nuclear Weapons:
NNSA Plans to Modernize Critical Depleted Uranium Capabilities and Improve Program ManagementGAO-21-16: Published: Oct 15, 2020. Publicly Released: Oct 15, 2020.
Jul 24, 2020
-
Nuclear Weapons:
Action Needed to Address the W80-4 Warhead Program's Schedule ConstraintsGAO-20-409: Published: Jul 24, 2020. Publicly Released: Jul 24, 2020.
Jun 24, 2020
-
National Nuclear Security Administration:
Analyzing Cost Savings Program Could Result in Wider Use and Additional Contractor EfficienciesGAO-20-451: Published: Jun 24, 2020. Publicly Released: Jun 24, 2020.
Jun 9, 2020
-
Nuclear Weapons:
NNSA Needs to Incorporate Additional Management Controls Over Its Microelectronics ActivitiesGAO-20-357: Published: Jun 9, 2020. Publicly Released: Jun 9, 2020.
May 13, 2020
-
Environmental Liabilities:
DOE Needs to Better Plan for Post-Cleanup Challenges Facing SitesGAO-20-373: Published: May 13, 2020. Publicly Released: May 13, 2020.
May 12, 2020
-
Hanford Waste Treatment Plant:
DOE Is Pursuing Pretreatment Alternatives, but Its Strategy Is Unclear While Costs Continue to RiseGAO-20-363: Published: May 12, 2020. Publicly Released: May 12, 2020.
Looking for more? Browse all our products here