Comments on a Plan for Obtaining Private Financing for the Clinch River Breeder Reactor
RCED-83-226: Published: Aug 22, 1983. Publicly Released: Sep 21, 1983.
Additional Materials:
- Full Report:
Contact:
In response to a congressional request, GAO presented a followup report of the progress of Department of Energy (DOE) plans to obtain private financing for the Clinch River Breeder Reactor (CRBR). In an earlier review, GAO had found that plans issued by DOE and the CRBR financing company in March 1983: (1) represented the beginning of a process that would require much more work and a tradeoff between short-term budgetary savings and possible higher overall Government costs for the project; and (2) did not provide sufficient information to adequately analyze the tax benefits of private financing.
GAO found that the private financing plan which DOE submitted to Congress on August 1, 1983, represented a more detailed version of the plan outlined in the March reports. The basic concept remains the same: with appropriate Government guarantees, the revenues from CRBR-generated electricity, and available tax benefits, investors could be found to finance a portion of the remaining CRBR cost. The revenues from the sale of CRBR-generated electricity will be used to pay back private investors and, if that revenue is inadequate, the plan calls for the Federal Government to provide all additional funds. The latest plan calls for the project to be a joint venture comprised of the Federal Government and a partnership of private investors. The plan anticipates that the initial private sector debt financing will be provided from $675 million in short-term, 10-percent construction loans from several large, private lenders. The CRBR financing company anticipates raising $150 million by selling equity shares in the CRBR. It also considers $175 million in utility contributions to be part of the $1 billion private investment package and the remaining undelivered portion of the utilities' original $257 million pledge. These latter funds would be provided for CRBR even if the private investment plan were not implemented. Tax benefits for the equity participants are better defined in the new plan. GAO concluded that, because the investors have not been identified, the net effect of private investment on tax revenues is uncertain.
Dec 10, 2020
-
Uranium Management:
Actions to Mitigate Risks to Domestic Supply Chain Could Be Better Planned and CoordinatedGAO-21-28: Published: Dec 10, 2020. Publicly Released: Dec 10, 2020.
Dec 8, 2020
-
Offshore Wind Energy:
Planned Projects May Lead to Construction of New Vessels in the U.S., but Industry Has Made Few Decisions amid UncertaintiesGAO-21-153: Published: Dec 8, 2020. Publicly Released: Dec 8, 2020.
Nov 19, 2020
-
Nuclear Waste Disposal:
Better Planning Needed to Avoid Potential Disruptions at Waste Isolation Pilot PlantGAO-21-48: Published: Nov 19, 2020. Publicly Released: Nov 19, 2020.
Oct 29, 2020
-
Nuclear Safety:
DOE and the Safety Board Should Collaborate to Develop a Written Agreement to Enhance OversightGAO-21-141: Published: Oct 29, 2020. Publicly Released: Oct 29, 2020.
Oct 15, 2020
-
Nuclear Weapons:
NNSA Plans to Modernize Critical Depleted Uranium Capabilities and Improve Program ManagementGAO-21-16: Published: Oct 15, 2020. Publicly Released: Oct 15, 2020.
Jul 24, 2020
-
Nuclear Weapons:
Action Needed to Address the W80-4 Warhead Program's Schedule ConstraintsGAO-20-409: Published: Jul 24, 2020. Publicly Released: Jul 24, 2020.
Jun 24, 2020
-
National Nuclear Security Administration:
Analyzing Cost Savings Program Could Result in Wider Use and Additional Contractor EfficienciesGAO-20-451: Published: Jun 24, 2020. Publicly Released: Jun 24, 2020.
Jun 9, 2020
-
Nuclear Weapons:
NNSA Needs to Incorporate Additional Management Controls Over Its Microelectronics ActivitiesGAO-20-357: Published: Jun 9, 2020. Publicly Released: Jun 9, 2020.
May 13, 2020
-
Environmental Liabilities:
DOE Needs to Better Plan for Post-Cleanup Challenges Facing SitesGAO-20-373: Published: May 13, 2020. Publicly Released: May 13, 2020.
May 12, 2020
-
Hanford Waste Treatment Plant:
DOE Is Pursuing Pretreatment Alternatives, but Its Strategy Is Unclear While Costs Continue to RiseGAO-20-363: Published: May 12, 2020. Publicly Released: May 12, 2020.
Looking for more? Browse all our products here