Poor Procurement Practices Resulted in Unnecessary Costs in Procuring M1 Tank Spares
PLRD-83-21: Published: Jan 18, 1983. Publicly Released: Jan 18, 1983.
Additional Materials:
- Full Report:
Contact:
(202) 275-4268
contact@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
GAO examined sole-source negotiated procurements for M1 tank spare components.
GAO found that, in its procurement of M1 tank spares, the Government incurred unnecessary costs because the contracting officer: (1) accepted ceiling prices for spares negotiated on a sole-source basis before obtaining cost or pricing data and then failed to change the ceiling prices once the cost data were received; (2) combined the sole-source spare ceiling prices with the one competitively established in the original contract; and (3) permitted inappropriate transfers of spares to other contracts. The last two actions resulted in decreasing the contractor's risk of exceeding the ceiling on the original contract price and in allowing the contractor an opportunity to recoup $5.6 million in costs to which it was not otherwise entitled. In addition, the contracting officer did not prepare and maintain memorandum records of negotiations as required by the Defense Acquisition Regulations (DAR).
Recommendations for Executive Action
Status: Closed - Implemented
Comments: DOD does not agree that GAO established a need to strengthen Defense guidance. It does agree that, if it is possible to strengthen guidance in this area, it should be done. Therefore, by June 30, 1984, DOD plans to review the present DAR coverage and, if needed, issue additional policy guidance. No further followup is necessary.
Recommendation: The Secretary of Defense should direct the Director, Defense Acquisition Regulatory Council, to strengthen Defense guidance on fixed-price incentive contracts by identifying circumstances which preclude combining ceiling prices under an existing contract with those established under modifications to those contracts, especially when the contract cost will exceed, or are expected to exceed, the target prices.
Agency Affected: Department of Defense
Status: Closed - Implemented
Comments: On November 3, 1983, the Deputy Undersecretary of Defense issued a memo to the three military departments requiring that a record of price negotiation be prepared at the conclusion of negotiation and that it address all significant issues discussed during negotiation. No further followup on this recommendation is necessary.
Recommendation: The Secretary of Defense should direct the Secretary of the Army to instruct M1 contracting officers of the importance of complying with the requirement in the DAR to prepare and maintain adequate memorandum records of the negotiations which demonstrate that the negotiated prices were fair and reasonable.
Agency Affected: Department of Defense
Explore the full database of GAO's Open Recommendations
»
Jan 19, 2021
-
GPS Modernization:
DOD Continuing to Develop New Jam-Resistant Capability, But Widespread Use Remains Years AwayGAO-21-145: Published: Jan 19, 2021. Publicly Released: Jan 19, 2021.
Jan 14, 2021
-
Columbia Class Submarine:
Delivery Hinges on Timely and Quality Materials from an Atrophied Supplier BaseGAO-21-257: Published: Jan 14, 2021. Publicly Released: Jan 14, 2021. -
Department of Defense:
Actions Needed to Improve Accounting of Intradepartmental TransactionsGAO-21-84: Published: Jan 14, 2021. Publicly Released: Jan 14, 2021.
Jan 12, 2021
-
DOD Critical Technologies:
Plans for Communicating, Assessing, and Overseeing Protection Efforts Should Be CompletedGAO-21-158: Published: Jan 12, 2021. Publicly Released: Jan 12, 2021.
Dec 10, 2020
-
Climate Resilience:
DOD Coordinates with Communities, but Needs to Assess the Performance of Related Grant ProgramsGAO-21-46: Published: Dec 10, 2020. Publicly Released: Dec 10, 2020. -
Electromagnetic Spectrum Operations:
DOD Needs to Address Governance and Oversight Issues to Help Ensure SuperiorityGAO-21-64: Published: Dec 10, 2020. Publicly Released: Dec 10, 2020.
Dec 2, 2020
-
Navy and Marine Corps:
Services Continue Efforts to Rebuild Readiness, but Recovery Will Take Years and Sustained Management AttentionGAO-21-225T: Published: Dec 2, 2020. Publicly Released: Dec 2, 2020.
Nov 20, 2020
-
GAO Audits Involving DOD:
Status of Efforts to Schedule and Hold Timely Entrance ConferencesGAO-21-185R: Published: Nov 20, 2020. Publicly Released: Nov 20, 2020.
Nov 19, 2020
-
Defense Acquisitions:
Joint Cyber Warfighting Architecture Would Benefit from Defined Goals and GovernanceGAO-21-68: Published: Nov 19, 2020. Publicly Released: Nov 19, 2020. -
Defense Intelligence:
Comprehensive Plan Needed to Improve Stakeholder Engagement in the Development of New Military Intelligence SystemGAO-21-57: Published: Nov 19, 2020. Publicly Released: Nov 19, 2020.
Looking for more? Browse all our products here