Navy Ships:
Status of SSN-21 Design and Lead Ship Construction Program
NSIAD-93-34: Published: Nov 17, 1992. Publicly Released: Nov 25, 1992.
Additional Materials:
- Full Report:
Contact:
(202) 512-3504
contact@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
Pursuant to a congressional request, GAO reviewed the Navy's Seawolf Nuclear Attack Submarine construction program, focusing on the: (1) status of the Seawolf's design; (2) status of major subsystem development efforts and their potential impact on the construction program; (3) cost, schedule, and performance status of the construction program; and (4) Seawolf's impact on the nuclear-powered attack submarine force and the U.S. submarine shipbuilding industrial base.
GAO found that: (1) the estimated costs for completing the SSN-21 design contract would increase by $352 million over the original contract cost of $303 million; (2) complexities in incorporating modular construction concepts into the SSN-21 design and the cost of two shipyards designing the submarine resulted in cost overruns and schedule delays; (3) cost growth and schedule revisions were primarily due to the late delivery of design data; (4) as of 1991, the SSN-21 design schedule had fallen behind by 500,000 hours, and only 3,970 of the 4,444 drawings had been issued due to a $75 million budget design reduction; (5) the SSN-21 design and construction schedule imbalance was eliminated due to the discovery and correction of hull and component part welding cracks; (6) welding cracks in submarine components increased the total cost by $68.6 million and delayed SSN-21 construction by 1 year; (7) the Navy cancelled two weapons systems intended for the SSN-21, rendering it less capable; and (8) the Navy cancelled planned procurements for two weapons systems for use on SSN-21 because one system failed to meet noise level specifications and the other system's high cost.
Matter for Congressional Consideration
Status: Closed - Not Implemented
Comments: Contract for SSN-22 was awarded. No request for SSN-21 class submarine funding was included in the FY 93 budget or planned for FY 94 budget.
Matter: If Congress decides to continue with more than one SSN-21 class submarine, it may wish to consider restricting the use of funds already appropriated for the second and third submarines. Further, Congress may wish to delay funding additional submarines until the design has stabilized and planned modifications to the MK-48 advanced capability torpedo's propulsion system and the AN/BSY-2 combat system development efforts have matured.
Recommendation for Executive Action
Status: Closed - Not Implemented
Comments: The contract for SSN-22 was awarded. No funds were requested for SSN-21 class submarines in the FY 1993 budget or planned for in the FY 1994 budget.
Recommendation: If Congress decides not to approve the administration's request to rescind funds appropriated for construction of follow-on SSN-21s, the Secretary of Defense should direct the Secretary of the Navy to provide Congress an assessment of the effect that problems in the lead ship design and construction and in subsystem and weapons system development will have on the cost, schedule, and performance of the follow-on SSN-21.
Agency Affected: Department of Defense
Explore the full database of GAO's Open Recommendations
»
Jan 13, 2021
-
Department of Energy Contracting:
Improvements Needed to Ensure DOE Assesses Its Full Range of Contracting Fraud RisksGAO-21-44: Published: Jan 13, 2021. Publicly Released: Jan 13, 2021.
Dec 16, 2020
-
Data Governance:
Agencies Made Progress in Establishing Governance, but Need to Address Key MilestonesGAO-21-152: Published: Dec 16, 2020. Publicly Released: Dec 16, 2020.
Dec 9, 2020
-
2020 Census:
The Bureau Concluded Field Work but Uncertainty about Data Quality, Accuracy, and Protection RemainsGAO-21-206R: Published: Dec 9, 2020. Publicly Released: Dec 9, 2020.
Dec 3, 2020
-
2020 Census:
Census Bureau Needs to Assess Data Quality Concerns Stemming from Recent Design ChangesGAO-21-142: Published: Dec 3, 2020. Publicly Released: Dec 3, 2020. -
2020 Census:
Census Bureau Needs to Ensure Transparency over Data QualityGAO-21-262T: Published: Dec 3, 2020. Publicly Released: Dec 3, 2020.
Nov 30, 2020
-
Federal Buying Power:
OMB Can Further Advance Category Management Initiative by Focusing on Requirements, Data, and TrainingGAO-21-40: Published: Nov 30, 2020. Publicly Released: Nov 30, 2020.
Nov 24, 2020
-
Disaster Response:
Agencies Should Assess Contracting Workforce Needs and Purchase Card Fraud RiskGAO-21-42: Published: Nov 24, 2020. Publicly Released: Nov 24, 2020.
Nov 23, 2020
-
Federal Contracting:
Actions Needed to Improve Department of Labor's Enforcement of Service Worker Wage ProtectionsGAO-21-11: Published: Oct 29, 2020. Publicly Released: Nov 23, 2020.
Nov 18, 2020
-
Federal Telework:
Key Practices That Can Help Ensure the Success of Telework ProgramsGAO-21-238T: Published: Nov 18, 2020. Publicly Released: Nov 18, 2020.
Oct 7, 2020
-
Unaccompanied Children:
Actions Needed to Improve Grant Application Reviews and Oversight of Care FacilitiesGAO-20-609: Published: Sep 15, 2020. Publicly Released: Oct 7, 2020.
Looking for more? Browse all our products here