Army Depots:
Plans Abandoned for the New Distribution Center at the Red River Depot
NSIAD-90-184: Published: Aug 20, 1990. Publicly Released: Aug 20, 1990.
Additional Materials:
- Full Report:
Contact:
(202) 512-3504
contact@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
Pursuant to a congressional request, GAO reviewed the Army's efforts to build highly mechanized distribution centers at three depots, focusing on: (1) the present work load at one depot compared to the Army's early projections; (2) the actual cost of that center; (3) the status of work at the three depots; and (4) the Army's rationale for completing one center, given the potential excess capacity at the other two centers.
GAO found that: (1) the projected work-load increases the Army used to justify constructing the new distribution centers did not materialize; (2) although the Army estimated that the total work load would increase by 26 percent to 53 percent over a 4-year period, it had remained at the 1985 level; (3) the actual work load at each depot was lower than the Army projected; (4) Army officials did not formally analyze the reasons for the discrepancy between projected and actual work loads, but partially attributed the discrepancy to budget cuts and more modern systems; (5) from 1985 through 1989, the number of stocked items at the three depots steadily increased, and most items were largely inactive; (6) depot productivity continued to increase despite a decline in work hours; (7) the estimated cost of three distribution centers has increased 35 percent since 1984, from about $488 million to about $658 million; (8) the Army terminated a construction contract for one center, since the other two centers had the capacity to handle the work load; and (9) the Army completed construction at two depots and one was partially operational, but the software needed to achieve full automation at two centers was in the testing stage.
Matter for Congressional Consideration
Status: Closed - Not Implemented
Comments: Congress declined to rescind unused funds, but did direct the Department of Defense (DOD) not to use or transfer any of the money for any purpose other than termination costs for the Red River Center. This action precludes DOD from using the funds which was the intent of the recommendation.
Matter: Because only about $8.7 million of the $90 million in military construction and procurement funds allocated for the now cancelled Red River center have been expended, and up to $18.6 million may be needed to terminate existing commitments, Congress may wish to consider rescinding the remaining $62.7 million, $42 million in military construction funds and $20.7 million in procurement funds.
Explore the full database of GAO's Open Recommendations
»
Jan 19, 2021
-
Federal Rulemaking:
Selected EPA and HHS Regulatory Analyses Met Several Best Practices, but CMS Should Take Steps to Strengthen Its AnalysesGAO-21-151: Published: Dec 17, 2020. Publicly Released: Jan 19, 2021.
Jan 13, 2021
-
Department of Energy Contracting:
Improvements Needed to Ensure DOE Assesses Its Full Range of Contracting Fraud RisksGAO-21-44: Published: Jan 13, 2021. Publicly Released: Jan 13, 2021.
Dec 16, 2020
-
Data Governance:
Agencies Made Progress in Establishing Governance, but Need to Address Key MilestonesGAO-21-152: Published: Dec 16, 2020. Publicly Released: Dec 16, 2020.
Dec 9, 2020
-
2020 Census:
The Bureau Concluded Field Work but Uncertainty about Data Quality, Accuracy, and Protection RemainsGAO-21-206R: Published: Dec 9, 2020. Publicly Released: Dec 9, 2020.
Dec 3, 2020
-
2020 Census:
Census Bureau Needs to Assess Data Quality Concerns Stemming from Recent Design ChangesGAO-21-142: Published: Dec 3, 2020. Publicly Released: Dec 3, 2020. -
2020 Census:
Census Bureau Needs to Ensure Transparency over Data QualityGAO-21-262T: Published: Dec 3, 2020. Publicly Released: Dec 3, 2020.
Nov 30, 2020
-
Federal Buying Power:
OMB Can Further Advance Category Management Initiative by Focusing on Requirements, Data, and TrainingGAO-21-40: Published: Nov 30, 2020. Publicly Released: Nov 30, 2020.
Nov 24, 2020
-
Disaster Response:
Agencies Should Assess Contracting Workforce Needs and Purchase Card Fraud RiskGAO-21-42: Published: Nov 24, 2020. Publicly Released: Nov 24, 2020.
Nov 23, 2020
-
Federal Contracting:
Actions Needed to Improve Department of Labor's Enforcement of Service Worker Wage ProtectionsGAO-21-11: Published: Oct 29, 2020. Publicly Released: Nov 23, 2020.
Nov 18, 2020
-
Federal Telework:
Key Practices That Can Help Ensure the Success of Telework ProgramsGAO-21-238T: Published: Nov 18, 2020. Publicly Released: Nov 18, 2020.
Looking for more? Browse all our products here