In response to a congressional request, GAO evaluated the Army's proposed changes to its approval process for equipment modification.

GAO found that under the proposed plan: (1) modifications exceeding $25 million would require approval by the Army acquisition executive; (2) the program executive officer, a new position in the acquisition management hierarchy, would approve modifications costing from $5 to $25 million; (3) project managers would be responsible for modifications of less than $5 million; (4) Army headquarters would no longer approve many low-cost product improvement programs; and (5) the Army Materiel Command would implement the changes. GAO believes that the plan would provide Army headquarters with added visibility over high-cost changes, while placing responsibility for low-cost modifications with project managers.

Mar 18, 2019

Mar 14, 2019

Mar 7, 2019

Mar 6, 2019

Feb 25, 2019

Feb 21, 2019

Feb 15, 2019

Looking for more? Browse all our products here