Embedded Computers:
Navy's Approach to Developing Patrol Aircraft Avionics System Too Risky
IMTEC-90-79: Published: Sep 28, 1990. Publicly Released: Oct 4, 1990.
Additional Materials:
- Full Report:
Contact:
(202) 512-6240
contact@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
Pursuant to a congressional request, GAO determined whether the: (1) Navy's Update IV Program provided for adequate pre-procurement testing of a new avionics computer system for P-3 and P-7 aircraft; and (2) Navy adequately oversaw the development of the embedded system.
GAO found that the Navy: (1) originally planned to thoroughly test the avionics system before buying more than four; (2) citing program delays, revised those plans and postponed complete testing; (3) allowed the Update IV contractor to develop software before it completed and approved subsystem specifications; (4) had approved only 3 of 93 software specifications, and projected that it would not approve all specifications before September 1990; (5) Update IV contractor was over a year late in developing two software integration laboratories for testing the system's acoustic and nonacoustic capabilities; (6) planned to buy 28 systems before it successfully completed all testing; (7) planned to test one of the system's processors using a model that did not accurately represent the final version; (8) failed to conduct any detailed analysis to support its belief that any further delays would cause it to miss fixed-price contract option deadlines and increase contract costs; and (9) failed to consider the costs of buying 28 systems that may not work as intended and may require expensive modifications. GAO also found that Update IV Program oversight authorities: (1) focused on the use of computer technology; and (2) have not granted final approval of the Navy's acquisition and testing plans.
Recommendations for Executive Action
Status: Closed - Implemented
Comments: The fiscal year (FY) 1991 appropriations bill reduced procurement funding for the P-3 aircraft by $68 million, in part due to the GAO report and subsequent congressional action. An accomplishment report will be prepared once FY 1992 congressional budget actions are complete. The expected completion date is November 1991.
Recommendation: The Secretary of the Navy should direct the Commander, Naval Air Systems Command, to: (1) halt further software development (i.e., coding) until system specifications are approved; (2) thoroughly justify the need for initial-rate production to exceed the four systems originally planned; (3) conduct initial operational testing using actual system components or accurate simulations of them; and (4) conduct full operational testing before making a full-rate production decision.
Agency Affected: Department of Defense: Department of the Navy
Status: Closed - Not Implemented
Comments: As of April 1, 1992, the fate of the Update IV Program was still being debated; however, the recommendation has been overtaken by events since Congress has completed its FY 1992 budget deliberations.
Recommendation: In light of the possibility that the previous recommendation may preclude the Navy from exercising existing, fixed-price contract options, the Secretary of the Navy should direct the Commander, Naval Air Systems Command, to thoroughly analyze the cost impact of contract renegotiation and, based on this analysis, decide whether the entire Update IV Program is financially viable.
Agency Affected: Department of Defense: Department of the Navy
Explore the full database of GAO's Open Recommendations
»
Dec 23, 2020
-
Information Technology:
DOD Software Development Approaches and Cybersecurity Practices May Impact Cost and ScheduleGAO-21-182: Published: Dec 23, 2020. Publicly Released: Dec 23, 2020.
Dec 15, 2020
-
Information Technology:
Federal Agencies Need to Take Urgent Action to Manage Supply Chain RisksGAO-21-171: Published: Dec 15, 2020. Publicly Released: Dec 15, 2020.
Oct 13, 2020
-
USAJOBS Website:
OPM Has Taken Actions to Assess and Enhance the User ExperienceGAO-21-31: Published: Oct 13, 2020. Publicly Released: Oct 13, 2020.
Oct 7, 2020
-
Information Technology:
IRS Needs to Address Operational Challenges and Opportunities to Improve ManagementGAO-21-178T: Published: Oct 7, 2020. Publicly Released: Oct 7, 2020.
Sep 30, 2020
-
Information Technology:
Selected Federal Agencies Need to Take Additional Actions to Reduce Contract DuplicationGAO-20-567: Published: Sep 30, 2020. Publicly Released: Sep 30, 2020.
Sep 29, 2020
-
Science & Tech Spotlight:
Agile Software DevelopmentGAO-20-713SP: Published: Sep 29, 2020. Publicly Released: Sep 29, 2020.
Sep 28, 2020
-
Agile Assessment Guide:
Best Practices for Agile Adoption and ImplementationGAO-20-590G: Published: Sep 28, 2020. Publicly Released: Sep 28, 2020.
Sep 14, 2020
-
Internet of Things:
Information on Use by Federal AgenciesGAO-20-577: Published: Aug 13, 2020. Publicly Released: Sep 14, 2020.
Sep 9, 2020
-
Medicaid Information Technology:
Effective CMS Oversight and States' Sharing of Claims Processing and Information Retrieval Systems Can Reduce CostsGAO-20-179: Published: Sep 9, 2020. Publicly Released: Sep 9, 2020.
Sep 8, 2020
-
Information Technology:
Key Attributes of Essential Federal Mission-Critical AcquisitionsGAO-20-249SP: Published: Sep 8, 2020. Publicly Released: Sep 8, 2020.
Looking for more? Browse all our products here