Joint Intelligence Analysis Complex:
DOD Partially Used Best Practices for Analyzing Alternatives and Should Do So Fully for Future Military Construction Decisions
GAO-16-853: Published: Sep 30, 2016. Publicly Released: Oct 31, 2016.
Additional Materials:
- Highlights Page:
- Full Report:
- Accessible Version:
Contact:
(202) 512-4523
leporeb@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
What GAO Found
The Department of Defense's (DOD) decision to consolidate and relocate its Joint Intelligence Analysis Complex (JIAC) to Royal Air Force (RAF) base Croughton in the United Kingdom (U.K.) was influenced by the JIAC's current facilities' deteriorating condition and DOD criteria that guided its analysis of alternatives (AOA). DOD determined the current facilities are not well suited to the JIAC's mission, in poor condition, and uneconomical to upgrade. In light of this, DOD's AOA process was driven by five criteria. Two of these—impact on intelligence operations and impact on bilateral and multinational intelligence collaboration—were considered critical, and three others—impact on international agreements and relationships, impact on community quality of life, and the business case for consolidation—important but secondary.
DOD's AOA process for JIAC consolidation fully or substantially met 6 best practices, partially or minimally met 15, and did not meet 1. Thus, it partially met the four characteristics encompassing these practices that GAO has identified as necessary to produce a high quality, reliable AOA process:
- Well documented: DOD's AOA process partially met the best practice of tying benefits or effectiveness to mission need, with a general explanation of how mission needs will be met under DOD's five AOA criteria. However, DOD minimally met the best practice of documenting the AOA process in a single document.
- Comprehensive: DOD's AOA process fully met the best practice of defining mission need, but minimally met the best practice of developing life cycle cost estimates. Specifically, DOD officials characterized the level of detail for its 2011 preliminary estimates as “extremely rough.”
- Unbiased: DOD's AOA process substantially met the best practice of ensuring that the process was impartial, in part because an independent DOD organization reviewed its conclusions. In contrast, DOD minimally met the best practice of comparing alternatives, as it did not provide evidence that all alternatives were evaluated against the same data.
- Credible: DOD's AOA process fully met the best practice of defining criteria, but minimally met the best practice of describing alternatives. Specifically, DOD's AOA body of work does not provide sufficient detail on each alternative to allow for robust analysis.
According to DOD officials, the department did not follow best practices when conducting its JIAC consolidation AOA process. This is because DOD does not have guidance outlining a set of AOA best practices for military construction decisions. Without guidance for using AOA best practices during certain military construction projects—such as those above a certain monetary threshold—DOD and Congress may face oversight challenges, and DOD may have trouble justifying its decisions for military construction projects in the future.
This is a public version of a classified report that GAO issued previously. It excludes classified information that provided additional detail on DOD's decision to consolidate the JIAC at RAF Croughton.
Why GAO Did This Study
DOD's JIAC, currently located at RAF Molesworth in the United Kingdom, provides critical intelligence support for the U.S. European and Africa Commands and U.S. allies.
GAO was asked to review DOD's decision to consolidate and relocate the JIAC to RAF Croughton, United Kingdom. This report 1) describes key considerations that influenced DOD's decision and 2) evaluates the extent to which DOD's AOA process for its JIAC consolidation project aligns with best practices for such analyses.
GAO visited current JIAC facilities to observe their condition and discuss with officials how certain factors affect the JIAC's ability to effectively conduct its mission, and the base at which DOD plans to consolidate the JIAC. GAO also discussed this AOA process with officials who participated in, and are knowledgeable about, the process; reviewed documentation used by DOD during the process; and evaluated the information using best practices identified by GAO as necessary characteristics of a high quality, reliable AOA process.
What GAO Recommends
GAO recommends that DOD develop guidance that requires the use of best practices—including those identified by GAO—when conducting AOA processes for certain future military construction projects. DOD did not agree, stating that the best practices do not apply to military construction project decision-making processes. GAO continues to believe that its recommendation is valid, as discussed in this report.
For more information, contact Brian J. Lepore at (202) 512-4523 or leporeb@gao.gov.
Recommendation for Executive Action
Status: Open

Comments: In its written comments, DOD did not concur with our recommendation. Specifically, DOD disputes that our 22 best practices for a reliable Analysis of Alternatives (AOA) process apply to basing or military construction decision-making processes and therefore does not believe that the department should incorporate these best practices into its military construction decision-making process. We continue to believe that our AOA best practices can be applied to a wide range of activities in which an alternative must be selected from a set of possible options, as well as to a broad range of capability areas, projects, and programs including DOD's military construction decision-making processes. As of June 22, 2017, DOD had not taken any action to implement this recommendation. As of July 2018, a senior DOD official said that DOD is developing a new analysis of alternatives (AOA) for JIAC consolidation and will use, as appropriate, our AOA best practices. We have requested information on the extent to which the AOA team is using the AOA best practices and will provide updated information when we confirm what actions DOD has taken.
Recommendation: To aid DOD in conducting future AOA processes that fully follow best practices, the Secretary of Defense should direct the Assistant Secretary of Defense for Energy, Installations, and the Environment to develop guidance requiring the use of AOA best practices, including those practices we have identified, and in this guidance, the Assistant Secretary should define the types of military construction decisions for which these AOA best practices should be required.
Agency Affected: Department of Defense
Explore the full database of GAO's Open Recommendations
»
Dec 26, 2018
-
DOD Depot Workforce:
Services Need to Assess the Effectiveness of Their Initiative to Maintain Critical Skills [Reissued with revisions on Dec. 26, 2018.]GAO-19-51: Published: Dec 14, 2018. Publicly Released: Dec 14, 2018.
Dec 20, 2018
-
Defense Science and Technology:
Actions Needed to Enhance Use of Laboratory Initiated Research AuthorityGAO-19-64: Published: Dec 20, 2018. Publicly Released: Dec 20, 2018.
Dec 19, 2018
-
Security Force Assistance:
U.S. Advising of Afghan National Army Has Expanded since 2015, and the U.S. Army Has Deployed a New Advising UnitGAO-19-251R: Published: Dec 19, 2018. Publicly Released: Dec 19, 2018.
Dec 17, 2018
-
Missile Defense:
Air Force Report to Congress Included Information on the Capabilities, Operational Availability, and Funding Plan for Cobra DaneGAO-19-68: Published: Dec 17, 2018. Publicly Released: Dec 17, 2018.
Dec 13, 2018
-
Military Personnel:
DOD Needs to Improve Dental Clinic Staffing Models and Evaluate Recruitment and Retention ProgramsGAO-19-50: Published: Dec 13, 2018. Publicly Released: Dec 13, 2018.
Dec 12, 2018
-
National Guard:
Office of Complex Investigations Should Update Policies to Require Additional Documentation for Sexual Assault CasesGAO-19-109: Published: Dec 12, 2018. Publicly Released: Dec 12, 2018. -
Navy and Marine Corps:
Rebuilding Ship, Submarine, and Aviation Readiness Will Require Time and Sustained Management AttentionGAO-19-225T: Published: Dec 12, 2018. Publicly Released: Dec 12, 2018.
Dec 4, 2018
-
Military Retirement:
Service Contributions Do Not Reflect Service Specific Estimated Costs and Full Effect of Proposed Legislation is UnknownGAO-19-195R: Published: Dec 4, 2018. Publicly Released: Dec 4, 2018.
Nov 30, 2018
-
Nuclear Weapons:
NNSA Has Taken Steps to Prepare to Restart a Program to Replace the W78 Warhead CapabilityGAO-19-84: Published: Nov 30, 2018. Publicly Released: Nov 30, 2018.
Nov 29, 2018
-
Maritime Security:
DOT Is Still Finalizing Strategy to Address Challenges to Sustaining U.S.-Flag FleetGAO-19-260T: Published: Nov 29, 2018. Publicly Released: Nov 29, 2018.
Looking for more? Browse all our products here

![defense icon, source: [West Covina, California] Progressive Management, 2008 defense icon, source: [West Covina, California] Progressive Management, 2008](https://www.gao.gov/images/rip/defense.jpg)
Explore our Key Issues on National Defense